●● Function of WBS. Answer: to divide the scope of work into
manageable parts that correspond to key deliverables, phases, or
milestones with the intent to avoid the omission of key elements and
assist in the communication of cost, schedule, quality, and resource
performance data to stakeholders.
●● Schedule Specification states. Answer: - Planning and scheduling
requirements and purposes
- Level of detail required
- Reporting periods and capabilities
- Minimum and mandatory scheduling tools
- Initial schedule development, submission, phasing and milestone
- Changes
- Claims and disputes
- Scheduler experience and qualification
- Requirements that the owner owner-client deems appropriate for
specific projects