LDP
Land Developing Projects - altering landscape for projects such as agriculture or housing
ect.
NPDES
National Pollutant Discharge Elimination System
- section of the CWA (Clean Water Act) to permit stormwater discharges associated w
industrial activities PER permit
CWA Penalty Types
Adminstrative
Class I. Neglegent
Class II. Knowlingly = greater fines
What documents are required on site?
- SWPPP
,- CGP
- Site Map
- Drawings and Key
- All inspection reports
- Any amendments to SWPPP
Who is the "operator"? Also the LRP.
Usually the OWNER of the site, not the contractor, unless authorized by the owner to
general contractor to have day-to-day operational control!
When do you need permit coverage?
Required from start to end of project. "End" being the final vegetative/non-vegetative
(concrete) stabilization occuring.
For any project one acre or greater.
Large Land Development
-strips off all existing vegetation a.k.a site carving
-usually on hillsides and steep slopes
-installation of untilities that tear up large areas of land
, Vertical Projects
- Homebuilding, smaller residence construction projects
-usually multiple subcontractors
-requires lots of housekeeping = mass choas
Bix Box Projects
-commercial buildings
-mass grading and mass choas
-highly visible w/ fairly large footprint
Linear Projects
-roadways, utilities, and stream corridors
-long narrow sites and mass choas
-limites site access and continually changing (high activity)
What is erosion?
The process by which soil particle get displaced by the act of wind of water.
What are the three types of Wind Erosion?
1. Creep - causes sand dunes