And Correct Answers
What is the purpose of installing an auxiliary boom point sheave to the main boom
tip?
Separate hoist lines
3 multiple choice options
A designated Lift Director shall be assigned by the ______?
Site Supervisor
3 multiple choice options
Who is responsible for calculating net capacity?
Crane Operator
3 multiple choice options
Who is responsible for ensuring all rigging is supervised by a Qualified Rigger?
Site Supervisor/ Lift Director
3 multiple choice options
,Who is responsible for ensuring the crane owner is notified of any damage to the
crane or replacement/repair of wire rope?
Crane User
3 multiple choice options
Who is responsible for restricting unauthorized access to the crane's work area?
Site Supervisor/Lift Director
3 multiple choice options
Who is responsible for ensuring the crane owner is notified of any damage to the
crane or replacement/repair of wire rope?
Crane User
3 multiple choice options
Who is responsible for ensuring crane operations are stopped if alerted to an unsafe
condition?
Lift Director
3 multiple choice options
If the operator or A/D determine that ground conditions are not suitable for the
equipment being operated, they should request the _________ correct the issue
,Controlling Entity
3 multiple choice options
Who is responsible for ensuring that personnel involved in crane operations
understand their responsibilities, assigned duties and associated hazards?
Lift Director
3 multiple choice options
When can the operator of a crane set the crane up with less than fully extended
outriggers?
When the load chart allows
3 multiple choice options
The outrigger pad and cribbing should be strong enough to support?
The total weight of the crane and the load
3 multiple choice options
What must be known prior to setting up your crane?
Location of underground vaults
3 multiple choice options
, What is the minimum distance the flange on the hoist drum should extend above the
last wrap of rope?
½ inch
3 multiple choice options
Eccentric main boom tip reeving will
Twisting of the boom
3 multiple choice options
What is the most common wire rope used on most cranes?
Right regular lay
3 multiple choice options
Prior to leveling a crane what should be done with the outrigger jack?
Secure the float pad to jack cylinder
3 multiple choice options
What three functions will not work after two-blocking a crane that has a prevention
system?
Boom down, extend the boom and hoist