Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

GEB 4522: ACG4101 Chapter 6B Homework Questions and Answers.

Beoordeling
-
Verkocht
-
Pagina's
8
Cijfer
A+
Geüpload op
05-05-2026
Geschreven in
2025/2026

Summary data for Benedict Construction Company's (BCC) Job 1227, which was completed in 2024, are presented below: Bid price $ 610,000 Contract cost: 2023 (244,000) 2024 (275,000) Gross profit: 91,000 Estimated cost to complete: 12/31/2023 $216,000 12/31/2024 $0 Assuming BCC recognizes revenue upon project completion, what would gross profit have been in 2023 and 2024 (rounded to the nearest thousand)? a. $42,782 | $48,218 b. $36,400 | $54,600 c. $74,277 | $16,723 d. $0 | $91,000 - Answer d. $0 | $91,000 No revenue is recognized until completion of project in 2024. Blue Co. had the following first-year amounts related to its $12,000,000 construction contract: Actual costs incurred and paid $3,000,000 Estimated remaining costs to complete $6,000,000 Progress billings $3,500,000 Cash collected $3,100,000 Assuming the contract qualifies for revenue recognition over time, what total amount (excluding cash) should Blue Co. recognize as current assets at year end? a. $0 b. $1,000,000 c. $900,000

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

GEB 4522: ACG4101 Chapter 6B
Homework Questions and Answers.
Summary data for Benedict Construction Company's (BCC) Job 1227, which was completed in
2024, are presented below:

Bid price $ 610,000

Contract cost:

2023 (244,000)

2024 (275,000)

Gross profit: 91,000

Estimated cost to complete:

12/31/2023 $216,000

12/31/2024 $0



Assuming BCC recognizes revenue upon project completion, what would gross profit have been
in 2023 and 2024 (rounded to the nearest thousand)?



a. $42,782 | $48,218

b. $36,400 | $54,600

c. $74,277 | $16,723

d. $0 | $91,000 - Answer d. $0 | $91,000



No revenue is recognized until completion of project in 2024.



Blue Co. had the following first-year amounts related to its $12,000,000 construction contract:

Actual costs incurred and paid $3,000,000

Estimated remaining costs to complete $6,000,000

Progress billings $3,500,000

Cash collected $3,100,000

Assuming the contract qualifies for revenue recognition over time, what total amount (excluding
cash) should Blue Co. recognize as current assets at year end?



a. $0

b. $1,000,000

c. $900,000

, d. $3,000,000 - Answer c. $900,000



When a long-term construction contract qualifies for revenue recognition over time, the entity
measures the progress toward completion by comparing total costs incurred to date,
$3,000,000, to total estimated costs, which consist of costs to date of $3,000,000 and estimated
remaining costs to complete of $6,000,000 for a total of $9,000,000. As a result, progress to
date is $3,000,000/$9,000,000 and the project is 1/3 complete.



With a contract price of $12,000,000 and an estimated cost of $9,000,000, estimated profit is
$3,000,000 and profit recognized to date will be 1/3 or $1,000,000. This is added to
construction in progress, resulting in an ending balance of $4,000,000. The entity will then
compare the balance in construction in progress to billings of $3,500,000, with the excess
reported as either a current asset or current liabilities. Since construction in progress of
$4,000,000 exceeds progress billings of $3,500,000 by $500,000, this amount will be reported as
a current asset, entitled something like Costs and profits in excess of billings.



In addition, the $3,500,000 billing created a current receivable, which was reduced by the
collections of $3,100,000 resulting in a receivable balance of $400,000. The total related current
assets are $500,000 + $400,000 or $900,000.



Sandlewood Construction Incorporated recognizes revenue over time according to percentage
of completion for its long-term construction contracts. In 2024, Sandlewood began work on a
$10,000,000 construction contract, which was completed in 2025. The accounting records
disclosed the following data at the end of 2024:



Costs incurred $5,400,000

Estimated cost to complete $3,600,000

Progress billings $4,100,000

Cash collections $3,200,000



How much gross profit should Sandlewood have recognized in 2024?



a. $0

b. $700,000

c. $1,000,000

d. $600,000 - Answer d. $600,000



As of year-end 2024, revenue recognized to date is ($5,400,000 ÷ ($5,400,000 + 3,600,000)) ×
$10,000,000 = $6,000,000, and cost of construction recognized to date is $5,400,000, so gross
profit recognized to date is $600,000.

Geschreven voor

Instelling
Vak

Documentinformatie

Geüpload op
5 mei 2026
Aantal pagina's
8
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$12.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TestSolver9 Webster University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
901
Lid sinds
2 jaar
Aantal volgers
127
Documenten
29063
Laatst verkocht
3 dagen geleden
TESTSOLVER9 STORE

TOPNOTCH IN LEARNING MATERIALS,(EXAMS,STUDYGUIDES NOTES ,REVIEWS,FLASHCARDS ,ALL SOLVED AND PACKAGED.OUR STORE MAKE YOUR EDUCATION JOURNEY EFFICIENT AND EASY.WE ARE HERE FOR YOU FEEL FREE TO REACH US OUT .

3.5

156 beoordelingen

5
67
4
20
3
27
2
13
1
29

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen