In which process does the activity 'evaluate the project' take place?
。Directing a project
。Closing a project
。Controlling a stage
。Managing a stage boundary - Answer Closing a project
Manual ref: 20.4.4
Course ref: S4-3P1
On behalf of whom do any appointed Project Assurance roles assure the project?
。Programme Director
。Project Manager
。Project Executive
。One or more members of the Project Board - Answer One or more members of the Project
Board
Manual ref: 7.2.1.5
Course ref: S3-2P1
When should the project board request a decision from corporate, programme management or
customer?
。If the senior supplier or senior user needs to be changed
。When the stage requires resources
。When any request for change need to be approved
。If it is forecast that project level tolerances will be exceeded - Answer If it is forecast that
project level tolerances will be exceeded
Manual ref: 12.2.1
,Course ref: S3-7P1
What is the purpose of a checkpoint report?
。Provides progress information on all of the work packages within a stage
。Updates the Project Manager on the status of a work package
。Records results of all quality checks and quality reviews held during the stage
。 Provides details of work packages to be issued before the next report is due - Answer
Updates the Project Manager on the status of a work package
Manual ref: Appendix A.4
Course ref: S3-7P1
Which of the following phrases are correct?
1. A project is normally cross-functional.
2. A project is likely to require a broad base of skills for a comparatively short period of time.
3. A project requires specialist skills to be developed over a long period of time.
4. Those providing a solutions will have different priorities to those with a problem to be solved
。All are correct
。Only 1, 2 and 3 are correct
。Only 2 and 4 are correct
。Only 1, 2 and 4 are correct - Answer Only 1, 2 and 4 are correct
Manual ref: Table 5.1
Course ref: S2-1P1
Which of these would you NOT expect to be part of a plan?
。Lessons incorporated
。Plan description
。Risks
。Product description - Answer Risks
,Manual ref: Appendix A.16
Course ref: S3-3P1
In which plan should closure activities be planned?
。Stage plan for the final management stage
。Initiation stage plan
。Team plan
。Plan for the second stage following project authorisation - Answer Stage plan for the final
management stage
Manual ref: 19.4.1
Course ref: S4-2P1
In which process is the quality management approach created?
。Controlling a stage
。Authorising a project
。Directing a project
。Initiating a project - Answer Initiating a project
Manual ref: 16.4.4
Course ref: S4-1P1
The quality management approach is written in which process?
。Directing a project
。Initiating a project
。Starting up a project
。Managing a stage boundary - Answer Initiating a project
Manual ref: 16.4.4
Course ref: S4-1P1
Which is a purpose of the risk management approach?
, 。To summarise exposure to strategic, programme, project and operational risks
。To define the techniques to be used when assessing project risks
。To recommend responses to each of the project risks
。To identify suitable risk owners for each of the project risks - Answer To define the
techniques to be used when assessing project risks
Manual ref: Appendix 24.1
Course ref: S3-4P1
From the products listed, which product is produced during starting up a project?
。The quality register
。The quality management approach
。The issue register
。The lessons log - Answer The lessons log
Manual ref: Figure 14.3
Course ref: S4-1P1
Which of the following progress controls is time driven?
。The highlight report
。The end stage report
。The end project report
。The exception report - Answer The highlight report
Manual ref: 12.2.2
Course ref: S3-7P1
How often does PRINCE2 recommend the the Issue register should be reviewed?
。As end stage assessments
。On a regular basis
。Weekly