C* - Answer Which role from the following list does PRINCE2® say cannot be delegated?
A. Team Manager
B. Project Assurance
C. Project Board Member
D. Project Support
*B* - Answer New versions of the Project Plan are produced at the end of each stage to
reflect updated information. Identify which option is FALSE.
A. Progress already made
B. Benefits already achieved
C. Any agreed changes in circumstances
D. Any revised forecast of cost
*B* - Answer The decision on whether a project's solution will be contracted to third parties
is made in which product?
A. The Project Plan
B. The Project Approach
C. The Project Brief
D. The Project Quality Plan
*C* - Answer Apart from "Initiating a Project" in which process is the Business Case
updated?
A. Managing Product Delivery
B. Controlling a Stage
C. Managing Stage Boundaries
D. Authorising a Stage
*B* - Answer What does PRINCE2® suggest may assist in the ultimate acceptance of the
project?
A. Identifying Risks associated with a plan
B. Agreeing the Quality Criteria for a product with the Customer
C. Establishing tolerance levels
, D. Follow-on Action Recommendations
*C* - Answer Which individual role is ultimately accountable for the project?
A. Project Manager
B. Senior Supplier
C. Executive
D. Senior User
*B* - Answer Who is responsible for the project producing a result that is capable of
achieving the benefits defined in the Business Case?
A. The Executive
B. The Project Manager
C. The Senior User
D. The entire Project Board
*B* - Answer In which document does PRINCE2® look for the identification of the Chairman
of a Quality Review?
A. Project Plan
B. Stage Quality Plan
C. Project Quality Plan
D. Project Initiation Document
*A* - Answer Which of the following quality measures is covered in the process "Initiating a
Project" (IP)?
A. How quality will be achieved
B. When each product will be tested
C. By whom each product will be tested
D. Options A, B and C
*C* - Answer In terms of configuration management what are described as the assets of a
project?
A. The resources
B. The plans
C. The products
D. The business benefits