|Latest Update with Complete Solution
k k k k k
Project Management – C783 k k k
k AHN1 Task 2 k k
Western Governors University k k
A. Provided is an explanation of the characteristics of the following contract types
k k k k k k k k k k k
(PMI, 2017):
k k
• Fixed price: This type of contract has a set price for the product or
k k k k k k k k k k k k k
service to be provided. Some of these contracts offer financial
k k k k k k k k k k
incentives for achieving or exceeding the goal. If there is a change in
k k k k k k k k k k k k k
the project's scope, the contract might be renegotiated with a higher
k k k k k k k k k k k
price.
k
• Time and materials: The time and materials type of contract has the
k k k k k k k k k k k
same components as both the fixed price contract and the cost-plus
k k k k k k k k k k k
contract. With this type of contract, the contractor or vendor is paid for
k k k k k k k k k k k k k
both their time and the cost of materials. When a time and materials
k k k k k k k k k k k k k
contract is used, this type of contract is most often an estimate, as
k k k k k k k k k k k k k
kthere can be price fluctuations in materials and time.
k k k k k k k k
• Cost plus: When a cost-plus contract is used, the project cost is for
k k k k k k k k k k k k
klabor and materials and would include a fixed fee paid to the contractor
k k k k k k k k k k k k
or vendor for overhead and profit.
k k k k k k
B. Five vendor selection criteria for the Merrilton Data Migration Project (PMI,
k k k k k k k k k k
2017).
k
1. Cost
2. Technical expertise k
3. Experience
4. Quality
5. Responsiveness
C. The purpose of Earned Value Analysis (EVA) is to assess the project's
k k k k k k k k k k k
performance and then identify potential future outcomes by using this analysis
k k k k k k k k k k k
to compare the planned work of the project against the actual project work that
k k k k k k k k k k k k k k
has been completed (PMI, 2017).
k k k k k
• Cost variance: When using the Earned Value Analysis, the cost variance
k k k k k k k k k k
can be factored in by comparing the project budget to the actual project
k k k k k k k k k k k k k
cost.
k
• Schedule variance: When using the Earned Value Analysis, the schedule
k k k k k k k k k
, variance can be factored by comparing the project schedule to the
k k k k k k k k k k k
actual schedule and progress of the project.
k k k k k k k
• Cost Performance Index: The Cost Performance Index (CPI) can be
k k k k k k k k k
factored into the EVA by determining the project's cost efficiency, and
k k k k k k k k k k k
you would use this formula to do so: CPI = EV/AC
k k k k k k k k k k k
• Scheduled Performance Index: The Scheduled Performance Index (SPI)
k k k k k k k
can be factored into the EVA by comparing the progress to the project
k k k k k k k k k k k k k
schedule.
k
1. How I would use EVA to monitor and control my project is that I would use
k k k k k k k k k k k k k k k
kall of the information provided to me to monitor and track my
k k k k k k k k k k k
projects, regarding the project timeline and schedule, and then work to
k k k k k k k k k k k
monitor for any indication that there is a potential for the project to
k k k k k k k k k k k k k
go over budget.
k k k