A 'place concrete' activity requires the placement of 2080 cubic yards. If the individual production rate is 2 cubic yards per work hour per person, with a 10-person crew and 8 hour workday, how many days are needed to complete this activity? a. 13 b. 26 c. 104 d. 130 - a. 13 A topographical map is a drawing showing? a. Subsurface soil conditions b. A general profile view of the site c. Contour lines and elevations d. Cross sections along the length of the project - c. Contour lines and elevations The owner's rep observed substandard drywall patches on a general contractor's renovation project. Which of the following should be the representative's first course of action? a. Save items for punch list b. Notify drywall finisher of the problem c. Tell painter not to accept patched walls. d. Notify general contractors superintend of problem - d. Notify general contractors superintend of problem Five Contractors are bidding part of a job with storm sewer, sanitary sewer, and water distribution. Their bids are: Contractor 1 will do storm and water for $2000. Contractor 2 will do storm for $1000. Contractor 3 will do sanitary and water for $12,000. Contractor 4 will do sanitary for $7,000 Contractor 5 will do water for $7,000 What is the lowest price for the complete job? a. $7,000 b. $9,000 c. $13,000 d. $15,000 - b. $9,000 Which of the following can be identified from the initial schedule of values? a. Vendors working on the project b. Contractors proposed breakdown of the project cost c. Profit margin of the applicant d. Quality of work in place - b. Contractors proposed breakdown of the project cost Who is primarily responsible for ensuring that contract documents comply with building codes? a. Owner b. Contractor c. Building inspector d. Architect design professional - d. Architect design professional What method is used to calculate activity duration? a. Daily production rate divided by plan quantity b. Plan quantity divided by crew rate c. Plan quantity divided by daily production rate d. Plan quantity dived by labor unit cost -

Meer zien Lees minder
Instelling
AIC
Vak
AIC

Voorbeeld van de inhoud

AIC Prep UH EXAM GUIDE QUESTIONS AND ANSWERS GRADED A



A 'place concrete' activity requires the placement of 2080 cubic yards. If the individual
production rate is 2 cubic yards per work hour per person, with a 10-person crew and 8
hour workday, how many days are needed to complete this activity?
a. 13
b. 26
c. 104
d. 130 - a. 13

A topographical map is a drawing showing?
a. Subsurface soil conditions
b. A general profile view of the site
c. Contour lines and elevations d. Cross sections along the length of the project - c.
Contour lines and elevations

The owner's rep observed substandard drywall patches on a general contractor's
renovation project. Which of the following should be the representative's first course of
action?
a. Save items for punch list
b. Notify drywall finisher of the problem
c. Tell painter not to accept patched walls.
d. Notify general contractors superintend of problem - d. Notify general contractors
superintend of problem

Five Contractors are bidding part of a job with storm sewer, sanitary sewer, and water
distribution. Their bids are: Contractor 1 will do storm and water for $2000. Contractor 2
will do storm for $1000. Contractor 3 will do sanitary and water for $12,000. Contractor
4 will do sanitary for $7,000 Contractor 5 will do water for $7,000 What is the lowest
price for the complete job?
a. $7,000
b. $9,000
c. $13,000
d. $15,000 - b. $9,000

Which of the following can be identified from the initial schedule of values?
a. Vendors working on the project
b. Contractors proposed breakdown of the project cost c. Profit margin of the applicant
d. Quality of work in place - b. Contractors proposed breakdown of the project cost

Who is primarily responsible for ensuring that contract documents comply with building
codes?
a. Owner

,AIC Prep UH EXAM GUIDE QUESTIONS AND ANSWERS GRADED A


b. Contractor
c. Building inspector
d. Architect design professional - d. Architect design professional

What method is used to calculate activity duration?
a. Daily production rate divided by plan quantity
b. Plan quantity divided by crew rate
c. Plan quantity divided by daily production rate
d. Plan quantity dived by labor unit cost - c. Plan quantity divided by daily production
rate

The architect has approved the rerouting of an HVAC through concrete slabs in a
building. To insure that activities are coordinated, a meeting should be called by the
field supervisor and the
a. HVAC subcontractor only
b. HVAC subcontractor and all other subcontractors
c. HVAC subcontractor and all other affected subcontractors
d. HVAC subcontractor and the architect engineer - c. HVAC subcontractor and all other
affected subcontractors

A project schedule has been updated. The activity placement of spread footing concrete
was originally scheduled to begin as early as day 10. The activity duration is 4 days.
The actual start day was day 12. The original schedule had calculated total float of 7
days for this activity. The recalculated total float for the activity, when updated, would be
a. 2 days
b. 5 days
c. 6 days
d. 9 days - b. 5 days

10. Under a design-build contract which of the following parties is responsible for
coordination of the design engineers and the subcontractors
a. Owner
b. Contractor
c. Architect
d. Subcontractor - b. Contractor

Concrete to be poured for 10 footings are 5 feet wide by 5 feet long by 2 feet deep. How
many cubic yards of concrete should the estimate be for this pour, using a 10%waste
factor.
a. 14.8
b. 16.3
c. 18.5
d. 20.3 - d. 20.3

,AIC Prep UH EXAM GUIDE QUESTIONS AND ANSWERS GRADED A


What is the term for a change order issued by the owner of a project that is outside of
the contractor's scope of work and therefore the contractor can a refuse to perform the
work?
a. Cardinal Change
b. Preliminary Change
c. No cost change order
d. Supplemental instructions - a. Cardinal Change

What is a "Schedule of Values"? a. A list of ethical practices in which employees may
participate
b. a table showing average wage rates for each crew
c. a breakdown of the contract amount into pay items
d. a list of construction activities - c. a breakdown of the contract amount into pay items

During layout of a site, it is determined that the slope distance between point A and
point B is 200 feet at a slope angle of 15 degrees. What is the actual horizontal distance
(H distance) on the plans from point A to point B?
a. 181.26'
b. 193.19'
c. 199.44'
d. 207.06' - b. 193.19'

According to CSI, which of the following is in the project manual?
a. General requirements
b. Estimate
c. schedule
d. Certificate of occupancy - a. General requirements

Which of the following are calculated by the "Backward pass" through the CPM
network?
a. Early start and late start
b. Total float and free float
c. Early start and early finish
d. Late start and late finish - d. Late start and late finish

Which of the following pre-bid information should be gathered for developing a bid
proposal? a. Schematic design, design development drawings, contract documents,
project manual, and bid documents
b. adjacent site conditions, existing surface conditions, existing utility locations, and field
dimensions
c. value engineering criteria, design outline specifications, total quality management
procedures, safety management procedures
d. shop drawings, product data sheets, samples, and submittal logs - a. Schematic
design, design development drawings, contract documents, project manual, and bid
documents

, AIC Prep UH EXAM GUIDE QUESTIONS AND ANSWERS GRADED A


Subcontractor "A" submits shop drawings to the GC which include materials that do not
comply with the contract documents. The GC as well as the architect stamps all of them
"reviewed". The materials are then shipped to the job site. During an off-loading
inspection, the GC notices the noncompliance. What action should the GC take
concerning the matter?
a. install them because the architect's stamp is a variance to the contract document
b. install them and ask for a discount from the subcontractor c. accept and install
materials
d. reject the shipment and require compliance with the contract documents - d. reject
the shipment and require compliance with the contract documents

Which of the following incorporates the tracking, confirming, and accelerating of delivery
of an item that has been purchased?
a. Routing
b. Expediting
c. Monitoring
d. Controlling - b. Expediting

How should a constructor establish the field staffing for a project?
a. in consultation with the architect and the owner
b. in Conformance with OSHA and ADA requirements
c. By reference to a cost manual
d. by utilization of past experience and schedule requirements - d. by utilization of past
experience and schedule requirements

if a schedule is accelerated, which of the following activities must be focused on first? a.
Critical activities b. Non critical Activities c. all activities with float time d. all activities
with the least costs - a. Critical activities

Which of the following provides the highest strength to dimensional lumber?
a. moisture content
b. age of wood
c. grain orientation
d. knots - c. grain orientation

Which of the following has the highest priority after a discovery on a Monday morning
that the job site has been vandalized and the magazine cases have been emptied of
explosives?
a. Call the insurance agent to see if damage is covered
b. Call the police to initiate an investigation
c. Pull the records on explosives stored on the site
d. Begin cleanup and repair the damage - b. Call the police to initiate an investigation

What is the point in the project when the architect has determined that the facility or a
portion of the facility is acceptable for owner use and occupancy?
a. Substantial completion date

Geschreven voor

Instelling
AIC
Vak
AIC

Documentinformatie

Geüpload op
5 mei 2026
Aantal pagina's
32
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$15.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
atiexpert A.T. Still University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
388
Lid sinds
3 jaar
Aantal volgers
270
Documenten
4113
Laatst verkocht
4 dagen geleden
@Nclex

SPECIALIZED ON; ####@NCLEX..........QA################################## [LATEST UPDATE 2022/2023 .ALL NCLEX EXAM AVAILABLE .HESI LATEST .ATI 100% CORRECT AND ALL RELATED HESI,NCLEX AND ATI TESTBANK ,BUNDLES AND FLASHCARDS]

3.9

64 beoordelingen

5
32
4
13
3
7
2
3
1
9

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen