• The purpose of Construction Quality Management is to: -✓✓Achieve the quality
established by properly developed requirements through the combined responsibility,
but seperate efforts of contractpr smd government personnel.
• Construction Quality Management is the performance of tasks, which ensure that
construction is performed. -✓✓According to plans and specifications, on time, within a
defined budget and a safe work environment.
• Partnering relationships are based upon: -✓✓Building trust and dedication to common
goals
• It is the responsibility of Quality Assurance Personnel to: -✓✓Periodically verify that
the contractors system of control is working effectively.
• An effective contractor quality control program will: -✓✓Be an incentive for work to be
done correctly the first time resulting in earlier completion, reduced field overhead costs,
and greater profits.
• The success or failure of all contractors is based upon: -✓✓The ability to control costs,
finance work, estimate jobs, schedule the work, and maintain effective quality control.
• Quality Assurance Personnel have the responsibility to: -✓✓Require contractors to
maintain the quality specified in the plans and specifications.
• Inspection is: -✓✓The process by which ongoing and completed work is examined
• During the punch-out inspection of a project: -✓✓Quality Assurance Personnel must
assure that the contractor prepares a punch-list and makes corrections.
• If there is a disagreement whether the contractors work complies with the contract: -
✓✓The government makes the final determination
• Characteristics that describe a definable feature of work include: -✓✓Cross-referenced
listings to the contractors construction schedule that may have more than one definable
feature under a section of the specifications.
• The _____________________ consists of daily checks of the work to assure
continuing compliance with contract requirements. -✓✓Follow-up phase