OVERVIEW DESCRIPTION:
The Construction Quality Management for Contractors (CQM-C) certification exam
validates that contractors working on USACE and NAVFAC projects understand their
mandatory quality control responsibilities, specifically the implementation of the three-
phase control system (Preparatory, Initial, and Follow-Up phases). The exam covers critical
topics including the development and execution of a project-specific Contractor Quality
Control (CQC) Plan, proper submittal management, distinction between contractor CQC
testing and government QA testing, documentation through daily reports and deficiency
logs, and the integration of safety into all QC phases.
QUESTION 1
Which of the following best describes the primary purpose of the CQM-C certification
for contractors working on USACE and NAVFAC projects?
A) To replace the government’s quality assurance role
B) To ensure the contractor understands QC requirements and can implement the three-
phase control system
C) To allow contractors to bypass submittal reviews
D) To certify electricians for specialized naval work
CORRECT ANSWER: B
EXPERT RATIONALE: CQM-C certification verifies that contractors know their QC
obligations and can properly execute the mandated three-phase control system on
USACE/NAVFAC projects.
,2|Page
QUESTION 2
During the Preparatory Phase of the three-phase control system, which action is most
critical?
A) Conducting daily follow-up inspections
B) Reviewing submittals, checking materials on-site, and verifying site readiness
C) Performing government QA testing
D) Issuing non-compliance reports
CORRECT ANSWER: B
EXPERT RATIONALE: The Preparatory Phase focuses on pre-work verification including
submittal review, material checks, and site readiness before any definable feature of
work begins.
QUESTION 3
What is the primary focus of the Initial Phase in the three-phase control system?
A) Final acceptance testing
B) Observing the beginning of a definable feature of work (DFOW) to confirm
compliance
C) Preparing the submittal register
D) Correcting rework items from previous phases
CORRECT ANSWER: B
EXPERT RATIONALE: The Initial Phase requires observation of the start of each DFOW to
ensure the work matches plans and specifications before full production proceeds.
QUESTION 4
During the Follow-Up Phase, what must the contractor’s QC personnel do on a daily
basis?
,3|Page
A) Rewrite the CQC plan
B) Perform daily checks to assure continued compliance with contract requirements
C) Submit a change order for any deviation
D) Only observe safety, not quality
CORRECT ANSWER: B
EXPERT RATIONALE: The Follow-Up Phase mandates daily inspections to confirm that
work remains compliant with the contract, extending from the initial setup through
completion.
QUESTION 5
Which document must the contractor develop and tailor to the specific project, covering
QC organization, personnel qualifications, and testing schedules?
A) The government’s Quality Assurance Plan
B) The Contractor Quality Control (CQC) Plan
C) The Safety Data Sheet (SDS)
D) The environmental impact statement
CORRECT ANSWER: B
EXPERT RATIONALE: The CQC Plan is a contractor-prepared, project-specific plan that
details QC organization, qualified personnel, and the testing frequency for all DFOWs.
QUESTION 6
What is the difference between CQC testing and QA testing on a USACE project?
A) CQC testing is done by the government; QA testing by the contractor
B) CQC testing is done by the contractor to verify contract compliance; QA testing is
done by the government
, 4|Page
C) Both are done by the same third-party lab
D) There is no difference; they are interchangeable terms
CORRECT ANSWER: B
EXPERT RATIONALE: Contractor Quality Control (CQC) testing is the contractor’s
responsibility to prove compliance, while government Quality Assurance (QA) testing
independently verifies results.
QUESTION 7
Who is responsible for managing the submittal register and distinguishing between
contractor-approved and government-approved submittals?
A) The government’s Contracting Officer only
B) The QC Manager and contractor’s team, per the CQC plan
C) The labor union representative
D) The project architect
CORRECT ANSWER: B
EXPERT RATIONALE: The contractor, through the QC Manager, must maintain the
submittal register and ensure proper handling of submittals that require contractor
approval versus those needing government approval.
QUESTION 8
Which role has the ultimate authority to stop work on a USACE contract for quality or
safety reasons?
A) The QC Manager
B) The project safety officer
C) The Contracting Officer (KO)
D) The subcontractor’s foreman