Consider a building which has 4 floors and multiple
basements. The recommended coded signal for the first
floor is _____? - Answer-2-1
(NFPA 72 Table A.10.11.4)
Consider a residential common area which is 30 feet x 50
feet which requires the use of strobes. The strobes are
ceiling mounted strobes. The ceiling is 10 feet AFF. A total
of _____ strobe(s) rated at 30 cd are required? - Answer-2
(NFPA 72 Table 18.5.5.4.1(a))
Consider a mechanical room which is 30 feet x 30 feet
which requires the use of strobes. The strobes are wall
mounted strobes. A total of _____ strobe(s) rated at 34 cd
are required? - Answer-1
(NFPA 72 Table 18.5.5.4.1(a))
Consider the installation of a protected premises fire alarm
system. All software and firmware shall be protected
,2|Page
against unauthorized access. Access by persons who
have a specific responsibility for safety and who are
trained to operate the control unit should be considered
Access Level _____? - Answer-4 (NFPA 72 A.23.2.2.2)
Consider a 120 feet x 150 feet room which has a ceiling
surface with beams which are 15 inches deep and spaced
at 4 feet apart. The ceiling is 14 feet AFF and level. The
beams run the parallel to the 150 foot length of the room.
Based on this a total of _____ smoke detectors are
required? - Answer-20 (NFPA 72 17.7.3.2.4.2(1))
NFPA 72 requires that two way telephone communications
service shall be capable of permitting the simultaneous
operation of any _____ telephone stations in a common
talk mode? - Answer-5 (NFPA 72.24.8.6)
The documentation for notification appliances shall identify
acoustically distinguishable spaces (ADS) when _____? -
Answer-Voice intelligibility is required
(NFPA 72 7.3.4.4)
,3|Page
Consider a corridor which is 10 feet wide with a smooth
and level ceiling. The maximum spacing between spot
type smoke detectors is _____ feet? - Answer-41
(NFPA 72 Figure A.17.6.3.1.1.1(g))
According to the IBC, a _____ is not considered a Use
Group I-1?
Convalescent facility
Alcohol and drug center
Halfway house
Psychiatric hospital - Answer-Psychiatric hospital
(IBC 308)
Consider the use of smoke detectors for door release. The
depth of the wall section above the door is 24 inches on
one side of the doorway. The depth of the wall section
above the door on the other side is 26 inches. Based on
this, the most appropriate smoke detector installation
according to NFPA 72 is _____? - Answer-One smoke
detector on the 26 inch side
(NFPA 72 17.7.56.51)
Wall mounted telephone appliances shall be not less than
_____ inches AFF? - Answer-36
, 4|Page
(NFPA 72 24.8.17)
Consider a control valve switch installed on a butterfly
valve. The off normal signal shall be initiated within _____
of the travel distance from the normal position? - Answer-2
revolutions
(NFPA 72 17.16.1.2)
Which of the following is an important contract provision?
(Select Three)
Contract price
Profit margin
Payment terms
Payment terms - Answer-Contract price
Payment terms
Payment terms
(Project management reference)
Which of the following is true regarding project
specifications? (Select Three)
They represent a legal contract.