NICET Fire Alarm Systems Certification Level IV Exam
ACTUAL VERIFIED EXAM COMPLETE QUESTIONS
AND CORRECT ANSWERS LATEST UPDATE.pdf
if the primary power is disconnected and the fire alarm
system goes into an alarm condition, what is the min
acceptable time for secondary power to operate the
emergency voice evacuation systems (EVACS) - Answer-
15 mins
a riser room temp switch should activate when the
temperature falls below which level? - Answer-40 degrees
F
according to NFPA72 what is the maximum sound
pressure level permitted in a space with notification
appliances? - Answer-110 dba
What is the min interval for testing a single station smoke
detector in multifamily units? - Answer-12 months
,2|Page
Where is a technician permitted to install a heat detector in
relation to a beam that is less than 12" deep and less then
8ft on center - Answer-on the bottom of the beam
An existing fire alarm cable in a drop ceiling will be
spliced. Which one of the following splice locations is
compliant with NFPA 70? - Answer-secured in a listed
fitting, box, or enclosure
Which function shall be tested for each newly installed
smoke detector? - Answer-sensitivity
When a device is inaccessible due to excessive height,
such as an atrium, what is the max interval for testing? -
Answer-18 months
When installing a wall-mounted fire telephone appliance to
the public, what is the acceptable max mounting height
from the floor? - Answer-48"
Elevator lobby smoke detectors shall be mounted within a
max of which distance from the centerline of the door? -
Answer-21'
,3|Page
At min, when working near power lines with voltage of
600v or lower, an aerial lift operator shall maintain which
distance from the lines? - Answer-10'
The use of unprotected EMT shall be permitted under
which conditions? - Answer-in dry, damp, and wet
locations
According to NFPA 70, what is the max unsupported
length of 1/2" flexible metallic conduit where flexibility is
requiered after installation? - Answer-3'
what is the max bend permitted in a conduit run between
outlet boxes - Answer-360 degrees
a 180ft long corridor is 10ft wide, with a smooth 10ft
ceiling, interrupted by 4in beams spaced every 10 ft. How
many heat detectors with a listed 30ft spacing are
required? - Answer-7
At which height must fire alarm cables be physically
protected when being installed within an exposed ceiling?
- Answer-7'
, 4|Page
When shall smoke detectors be installed during the
construction process? - Answer-after final cleanup of all
trades
Where structural members are provided, intermediate
metal conduit shall be secured within which max distance
from an outlet box? - Answer-3'
What is the max operating temp of TW insulation? -
Answer-60 degrees C
which type of meter is used to measure the current draw
of a strobe circuit? - Answer-multimeter
Which three of the following conditions are symptoms of a
heart attack?
A)Heartburn
B)Pain in chest
C)Shortness of breath
D) Seizures - Answer-A