1. What is the PRIMARY responsibility of a project manager on a construction
project?
A. Perform all labor tasks
B. Oversee project scope, schedule, cost, and safety
C. Only manage finances
D. Only supervise workers
Answer: B
Rationale: Project managers coordinate all major project elements.
2. A project is falling behind schedule. What is the FIRST action the project
manager should take?
A. Ignore delay
B. Analyze schedule and identify critical path delays
C. Increase cost immediately
D. Fire workers
Answer: B
Rationale: Identifying root cause allows corrective action.
,3. What is the critical path in a project schedule?
A. Shortest tasks
B. Longest sequence of dependent activities determining project duration
C. Cheapest tasks
D. Optional tasks
Answer: B
Rationale: Critical path controls project timeline.
4. A contractor exceeds budget due to poor planning. What was MOST likely
missing?
A. Communication
B. Accurate cost estimation
C. Safety plan
D. Workforce
Answer: B
Rationale: Budget overruns often stem from inaccurate estimates.
5. What is the PRIMARY purpose of a project scope statement?
A. Increase cost
B. Define project boundaries and deliverables
C. Control schedule only
D. Reduce workforce
Answer: B
Rationale: Scope defines what is included in the project.
6. A subcontractor delays work due to material shortage. What should the
project manager do FIRST?
A. Ignore
B. Identify cause and coordinate material delivery
, C. Terminate contract
D. Increase schedule duration
Answer: B
Rationale: Coordination resolves supply chain issues.
7. What is the MOST important purpose of a project schedule?
A. Decoration
B. Plan and track progress of tasks
C. Increase cost
D. Reduce labor
Answer: B
Rationale: Schedules guide project execution.
8. A project manager identifies risks early. What is the benefit?
A. Increased delays
B. Ability to mitigate potential issues
C. Higher cost
D. Reduced safety
Answer: B
Rationale: Risk management prevents problems.
9. What is the PRIMARY purpose of a contract in construction?
A. Decoration
B. Define legal responsibilities and obligations
C. Increase cost
D. Reduce schedule
Answer: B
Rationale: Contracts protect all parties legally.