Teamwork can be defined as: ✔Correct Answer-A process whereby people work
collaboratively towards a common goal
A leader should: ✔Correct Answer-Provide constructive and immediate feedback on
individual team members
For which of the following types is project management best suited? ✔Correct Answer-
Introducing change
What is a project management process? ✔Correct Answer-a. A defining and planning process
b. A monitoring and controlling process
d. A starting or initiating process
What is a major component of programme management? ✔Correct Answer-Benefits
management
A portfolio can best be defined as: ✔Correct Answer-a group of projects and programmes
carried out within an organisation
Project context refers to: ✔Correct Answer-The environment within which a project is
undertaken
A project life cycle: ✔Correct Answer-Consists of a number of distinct phases
Closure is best described as: ✔Correct Answer-The process of finalising all project matters
The group or individual who is ultimately accountable for a project is: ✔Correct Answer-The
sponsor
What is a responsibility of the project manager: ✔Correct Answer-Delivers the project
objectives to enable benefits to be realised
Project sponsorship is concerned with: ✔Correct Answer-Identifying the business need
Estimating by use of a detailed Work Breakdown Structure (WBS) is known as: ✔Correct
Answer-Bottom-up estimating
, The business case is owned by: ✔Correct Answer-The project sponsor
Appropriate focus on the project success factors will: ✔Correct Answer-Increase the
likelihood of a successful project
A stakeholder is best described as: ✔Correct Answer-Someone with power who has an
interest in the success or failure of the project
A project management plan (PMP) is first written: ✔Correct Answer-During the definition
phase
Project reporting can be defined as a process that: ✔Correct Answer-Presents information in
an appropriate format and formally communicates it to stakeholders
What would the work breakdown structure be most suitable for? ✔Correct Answer-Defining
all the activities of the project
Configuration management consists of: ✔Correct Answer-Planning, identification, control,
status accounting, audit
What best describes procurement? ✔Correct Answer-The process by which goods and
services required by a project are acquired
The critical path through a network: ✔Correct Answer-Always has the minimum total float
Resource management in teams is most concerned with ensuring: ✔Correct Answer-The right
persons are in place when required and used efficiently
Resource smoothing is best described as: ✔Correct Answer-A process to ensure that
resources are used as efficiently as possible by minimising peaks and troughs
Which one of the following best describes a project issue? ✔Correct Answer-A threat to the
project which cannot be resolved by the project manager
Risks are assessed according to: ✔Correct Answer-Their impact and likelihood
What forms part of quality management? ✔Correct Answer-b. Quality planning
c. Quality assurance
d. Continuous improvement
What is a good reason for the post-project appraisal? ✔Correct Answer-To improve future
project management performance