1. What is the primary purpose of project integration management?
A. Managing project procurement contracts
B. Coordinating all project elements into a unified whole
C. Developing only the project schedule
D. Assigning team roles and responsibilities
Answer: B. Coordinating all project elements into a unified whole
Rationale: Integration management ensures that all parts of the project work
together and are properly coordinated.
2. Which document formally authorizes a project?
A. Project scope statement
B. Business case
C. Project charter
D. Work breakdown structure
,Answer: C. Project charter
Rationale: The project charter officially authorizes the project and gives the
project manager authority.
3. What is the main output of the Define Scope process?
A. Cost baseline
B. Project charter
C. Project scope statement
D. Risk register
Answer: C. Project scope statement
Rationale: The scope statement defines what is included and excluded in the
project.
4. What is the purpose of a Work Breakdown Structure (WBS)?
A. Assign project budget
B. Break project work into manageable components
C. Identify project risks
D. Approve procurement contracts
Answer: B. Break project work into manageable components
Rationale: WBS decomposes deliverables into smaller, manageable work
packages.
5. Which process defines how project scope is validated?
A. Control Scope
B. Validate Scope
C. Define Scope
D. Collect Requirements
Answer: B. Validate Scope
Rationale: Validate Scope ensures deliverables are accepted by stakeholders.
, 6. What is a baseline used for in project management?
A. A random estimate
B. A final approved version for comparison
C. A risk document
D. A communication plan
Answer: B. A final approved version for comparison
Rationale: Baselines serve as approved standards for scope, schedule, and cost
comparison.
7. What is the critical path in a project schedule?
A. The shortest path
B. The most expensive tasks
C. The longest duration path with zero slack
D. The easiest tasks
Answer: C. The longest duration path with zero slack
Rationale: The critical path determines the shortest possible project duration.
8. What tool is commonly used for sequencing activities?
A. Histogram
B. Network diagram
C. Fishbone diagram
D. Pareto chart
Answer: B. Network diagram
Rationale: Network diagrams show dependencies between project activities.
9. What does resource leveling aim to do?
A. Increase project scope