A cumulative list of job deficiencies/rework items can be
found in: - correct answer- A deficiency
tracking system/reworks items list that is typically
maintained in RMS.
A definable feature of work: - correct answer-
Can consist of a combination of multiple specification
sections depending upon the nature of the work
Actual construction on the job site begins: - correct
answer- After an interim or final QC Plan is
accepted.
All submittals for government approval must be provided
by the _________________ in time to allow for the
review, approval, procurement, delivery, and
performance of preparatory phase for an item before it is
, needed for construction. - correct answer-
Contractor to the Government
An effective contractor quality control (CQC) program will:
- correct answer- Be an incentive for work to be
done correctly the first time resulting in earlier
completion, reduced field overhead costs, and greater
profits
Characteristics that describe a definable feature of work
(DFOW) include: - correct answer- *Cross-
referenced listings to the contactor's construction
schedule that may have more than one definable feature
under a section of the specifications.* /// Task that is
separate and distinct from other tasks which have
separate quality control requirement
Construction Quality Management is the performance of
tasks, which ensure that construction is performed. -
correct answer- According to plans and
specifications, on time, within a defined budget and a safe
work environment.