with all Correct & 100% Verified Answers
one who leads the tam but rather than directing project team members, they act as a facilitator
who ensures that obstacles are removed and the team has the resources needed to complete
the iteration ✔Correct Answer-scrum master
where the focus is to work together in delivering functionality to the customer in a relatively
short period of time (often less than 3 weeks) ✔Correct Answer-sprints
a system in which customer functionality requirement are written down and then the customer
prioritizes them so that the team knows what to work on first ✔Correct Answer-backlog
the daily standup meeting where the team discusses their work status and plans the work for
the day ✔Correct Answer-scrum
a discussion after the completion of each sprint to determine what went well and what changes
should occur in the next sprint ✔Correct Answer-retrospective
True or false? Agile project management methods have been particularly successful with the
development of software and new products. ✔Correct Answer-True
True or false? With agile project management methods, teams stay together for the duration.
✔Correct Answer-True
In agile project management terminology, the backlog is updated with ________. ✔Correct
Answer-user stories
Because it involves delivering a project after repeated short bursts of work, agile project
management is considered a(n) ________ approach to project management. ✔Correct
Answer-iterative
A potential challenge of using agile project management methods is that they depend heavily
on the regular availability and ________ of the customer. ✔Correct Answer-decisiveness
True or false? An agile project management approach would be effective in situations where the
customer is likely to change the scope. ✔Correct Answer-True
Agile project management methods are know for being ________ to changes in customer needs
and the project environment. ✔Correct Answer-responsive