PJM GENERATION DISPATCHER SAMPLE EXAM
ACTUAL 2026 QUESTIONS AND VERIFIED
ANSWERS
Save
Terms in this set (35)
Real time transmission constraints D. off cost ( out of merit )
or contingencies may be alleviated
with generators operating :
A. below 60 hertz
B. on a new price curve
C. on a new cost curve
D. off cost ( out of merit)
Monitoring LMP may give insights A. system constraints
into :
A. system constraints
B. system voltage
C. system frefuency
D. time error
, PJM calls for which of the following B. synchronized Reserves
to recover the ACE so that tie line
schedules are maintained ?
A. IRC ( instantaneous reserve
check )
B. synchronized Reserves
C. supplemential reserves
D. minimun generation calculation
If not cancelled by PJM , the A. at the end of the specified light load period
minimum generation alert expires :
A. at the end of the specified light
load period
B. when notified by NERC
C. 12 hours after the alert was
issued
D. after a 24 hour period
ACTUAL 2026 QUESTIONS AND VERIFIED
ANSWERS
Save
Terms in this set (35)
Real time transmission constraints D. off cost ( out of merit )
or contingencies may be alleviated
with generators operating :
A. below 60 hertz
B. on a new price curve
C. on a new cost curve
D. off cost ( out of merit)
Monitoring LMP may give insights A. system constraints
into :
A. system constraints
B. system voltage
C. system frefuency
D. time error
, PJM calls for which of the following B. synchronized Reserves
to recover the ACE so that tie line
schedules are maintained ?
A. IRC ( instantaneous reserve
check )
B. synchronized Reserves
C. supplemential reserves
D. minimun generation calculation
If not cancelled by PJM , the A. at the end of the specified light load period
minimum generation alert expires :
A. at the end of the specified light
load period
B. when notified by NERC
C. 12 hours after the alert was
issued
D. after a 24 hour period