LADOTD Highway Plan Reading I Exam
Questions With Correct Answers
1-1a: The CONTRACT covering the construction project is a(n) _____ between
| | | | | | | | | | |
LADOTD and the contractor. - CORRECT ANSWER✔✔-Written agreement
| | | | | | |
1-1b: Which document asks the contractor to submit a cost bid for a project? -
| | | | | | | | | | | | | | |
CORRECT ANSWER✔✔-Invitation to Bid
| | |
1-1c: Contractors base their bid on the materials and labor necessary to construct
| | | | | | | | | | | |
the highway project. Which document tells the contractor WHAT to construct and
| | | | | | | | | | | |
WHERE to construct it? - CORRECT ANSWER✔✔-Plans
| | | | | | |
1-1d: List the three categories regarding specs for a project - CORRECT
| | | | | | | | | | | |
ANSWER✔✔-Standard, Supplemental, Special | |
1-1e: After the contractor completes an estimate, they fill out and submit a _____
| | | | | | | | | | | | |
- CORRECT ANSWER✔✔-Proposal
| | |
1-1f: The Dept issues a(n) _____ allowing the contractor to start a project. -
| | | | | | | | | | | | | |
CORRECT ANSWER✔✔-Notice to Proceed
| | |
1-1g: What can change the contract after the start of the project? - CORRECT
| | | | | | | | | | | | | |
ANSWER✔✔-Plan Changes/Special Agreements | |
,1-1h: Which documents are the most referenced when used to inspect; what,
| | | | | | | | | | | |
where, and how the contractor builds? - CORRECT ANSWER✔✔-Plans
| | | | | | | |
1-1i: Record the name of the document the project engineer prepares when a
| | | | | | | | | | | | |
change in plans is required. - CORRECT ANSWER✔✔-Change Orders
| | | | | | | |
Occasionally, a contractor must preform extra work, to complete the project.
| | | | | | | | | | |
Prior to the contractor performing the work, the Chief Engineer signs a _______. -
| | | | | | | | | | | | |
CORRECT ANSWER✔✔-Change order
| | |
1-2a: Which specs apply to only a specific project under contract? - CORRECT
| | | | | | | | | | | | |
ANSWER✔✔-Special Provisions |
1-2b: What specs apply to all projects? - CORRECT ANSWER✔✔-Standard Specs
| | | | | | | | | |
1-2c: Special directions applicable to specific projects are _____. - CORRECT
| | | | | | | | | | |
ANSWER✔✔-Special Specs |
1-2d: A revision or amendment to the Standard Specs is a ______. - CORRECT
| | | | | | | | | | | | | |
ANSWER✔✔-Supplemental Specs |
1-3a (1-4): List the PROCEDURAL ORDER TO FOLLOW with regard to the
| | | | | | | | | | | |
clarification of possible contract discrepancies. - CORRECT ANSWER✔✔-1.
| | | | | | | |
Special, 2. Plans, 3. Supplemental, 4.Standard
| | | | |
, 1-4a: To read a set of plans it is important to accurately _____ and understand
| | | | | | | | | | | | | | |
what is meant by each drawing an notation. - CORRECT ANSWER✔✔-Interpret
| | | | | | | | | |
1-4b: The plans indicate ____ to build and _____ to build a project. - CORRECT
| | | | | | | | | | | | | | |
ANSWER✔✔-What and Where | |
1-4c: Sheets within a set of plans _____ to each other. Info pertaining to a
| | | | | | | | | | | | | | |
particular feature of the project often appears on more than one sheet. -
| | | | | | | | | | | | |
CORRECT ANSWER✔✔-Relate |
1-4d:It is very important to keep a plan set _____ and in _____. - CORRECT
| | | | | | | | | | | | | | |
ANSWER✔✔-Clean and in order | | |
2-2a. There are two types of project numbers used to identify a project. (DRAIN
| | | | | | | | | | | | | |
CANAL BRIDGES ON US HWY 90) - CORRECT ANSWER✔✔-Federal, State
| | | | | | | | |
2-4a. List the three things on the Title Sheet that identify a project. (DRAIN
| | | | | | | | | | | | | |
CANAL BRIDGES ON US HWY 90) - CORRECT ANSWER✔✔-State Project #, Federal
| | | | | | | | | | | |
Project #, Project Name
| | |
2-6a. List three places on the Title Sheet that indicate the State Project Number.
| | | | | | | | | | | | | |
(DRAIN CANAL BRIDGES ON US HWY 90) - CORRECT ANSWER✔✔-Project Caption,
| | | | | | | | | |
|Title Block, Layout Map
| | |
2-8. Prefix Acronyms such as STP, I, BR, etc are ______. - CORRECT ANSWER✔✔-
| | | | | | | | | | | | |
Federal-funding categories |
Questions With Correct Answers
1-1a: The CONTRACT covering the construction project is a(n) _____ between
| | | | | | | | | | |
LADOTD and the contractor. - CORRECT ANSWER✔✔-Written agreement
| | | | | | |
1-1b: Which document asks the contractor to submit a cost bid for a project? -
| | | | | | | | | | | | | | |
CORRECT ANSWER✔✔-Invitation to Bid
| | |
1-1c: Contractors base their bid on the materials and labor necessary to construct
| | | | | | | | | | | |
the highway project. Which document tells the contractor WHAT to construct and
| | | | | | | | | | | |
WHERE to construct it? - CORRECT ANSWER✔✔-Plans
| | | | | | |
1-1d: List the three categories regarding specs for a project - CORRECT
| | | | | | | | | | | |
ANSWER✔✔-Standard, Supplemental, Special | |
1-1e: After the contractor completes an estimate, they fill out and submit a _____
| | | | | | | | | | | | |
- CORRECT ANSWER✔✔-Proposal
| | |
1-1f: The Dept issues a(n) _____ allowing the contractor to start a project. -
| | | | | | | | | | | | | |
CORRECT ANSWER✔✔-Notice to Proceed
| | |
1-1g: What can change the contract after the start of the project? - CORRECT
| | | | | | | | | | | | | |
ANSWER✔✔-Plan Changes/Special Agreements | |
,1-1h: Which documents are the most referenced when used to inspect; what,
| | | | | | | | | | | |
where, and how the contractor builds? - CORRECT ANSWER✔✔-Plans
| | | | | | | |
1-1i: Record the name of the document the project engineer prepares when a
| | | | | | | | | | | | |
change in plans is required. - CORRECT ANSWER✔✔-Change Orders
| | | | | | | |
Occasionally, a contractor must preform extra work, to complete the project.
| | | | | | | | | | |
Prior to the contractor performing the work, the Chief Engineer signs a _______. -
| | | | | | | | | | | | |
CORRECT ANSWER✔✔-Change order
| | |
1-2a: Which specs apply to only a specific project under contract? - CORRECT
| | | | | | | | | | | | |
ANSWER✔✔-Special Provisions |
1-2b: What specs apply to all projects? - CORRECT ANSWER✔✔-Standard Specs
| | | | | | | | | |
1-2c: Special directions applicable to specific projects are _____. - CORRECT
| | | | | | | | | | |
ANSWER✔✔-Special Specs |
1-2d: A revision or amendment to the Standard Specs is a ______. - CORRECT
| | | | | | | | | | | | | |
ANSWER✔✔-Supplemental Specs |
1-3a (1-4): List the PROCEDURAL ORDER TO FOLLOW with regard to the
| | | | | | | | | | | |
clarification of possible contract discrepancies. - CORRECT ANSWER✔✔-1.
| | | | | | | |
Special, 2. Plans, 3. Supplemental, 4.Standard
| | | | |
, 1-4a: To read a set of plans it is important to accurately _____ and understand
| | | | | | | | | | | | | | |
what is meant by each drawing an notation. - CORRECT ANSWER✔✔-Interpret
| | | | | | | | | |
1-4b: The plans indicate ____ to build and _____ to build a project. - CORRECT
| | | | | | | | | | | | | | |
ANSWER✔✔-What and Where | |
1-4c: Sheets within a set of plans _____ to each other. Info pertaining to a
| | | | | | | | | | | | | | |
particular feature of the project often appears on more than one sheet. -
| | | | | | | | | | | | |
CORRECT ANSWER✔✔-Relate |
1-4d:It is very important to keep a plan set _____ and in _____. - CORRECT
| | | | | | | | | | | | | | |
ANSWER✔✔-Clean and in order | | |
2-2a. There are two types of project numbers used to identify a project. (DRAIN
| | | | | | | | | | | | | |
CANAL BRIDGES ON US HWY 90) - CORRECT ANSWER✔✔-Federal, State
| | | | | | | | |
2-4a. List the three things on the Title Sheet that identify a project. (DRAIN
| | | | | | | | | | | | | |
CANAL BRIDGES ON US HWY 90) - CORRECT ANSWER✔✔-State Project #, Federal
| | | | | | | | | | | |
Project #, Project Name
| | |
2-6a. List three places on the Title Sheet that indicate the State Project Number.
| | | | | | | | | | | | | |
(DRAIN CANAL BRIDGES ON US HWY 90) - CORRECT ANSWER✔✔-Project Caption,
| | | | | | | | | |
|Title Block, Layout Map
| | |
2-8. Prefix Acronyms such as STP, I, BR, etc are ______. - CORRECT ANSWER✔✔-
| | | | | | | | | | | | |
Federal-funding categories |