Quizzes | Answered latest spring 26.
Module 4 – Resource Allocation Process
Question 5 of 5
After the Congress passes the DoD Appropriations Bill and the President signs it, the
Office of Management and Budget (OMB) distributes the Budget Authority to the DoD.
What is this distribution called?
• Apportionment
• Acknowledgment
• Aggregation
• Authorization
Correct Answer: Apportionment
Module 5 – Financial Management
Question 5 of 6
The Life Cycle Cost Estimate (LCCE) uses the work breakdown structure to show costs by
system and subsystem.
• True
• False
Correct Answer: True
, Question 6 of 6
Which of the following appropriations categories fund the Research and Development
efforts performed by both contractors and government agencies?
• MILPERS
• Procurement
• Research, Development, Test and Evaluation
• Operations and Maintenance
Correct Answer: Research, Development, Test and Evaluation
Module 6 – Contracting
Question 1 of 7
A Fixed-Price contract includes which of the following characteristics:
• Written primarily as a contractual instrument with a price ceiling that authorizes
the contractor to start work immediately, Negotiating a definitive contract is not
possible in sufficient time to meet the requirements
• A Low cost to the government. Guaranteed delivery by the contractor, well-
defined requirements
• Higher cost to the government. Requirements may not be well defined. Payment
as costs are incurred
• Time of delivery is unspecified in the original contract. Flexible delivery schedules.
Permits flexible quantities that are purchased from the contractor
Correct Answer: A Low cost to the government. Guaranteed delivery by the
contractor, well-defined requirements