• The person in charge of the utility company, municipality, or other public or private
company or agency that owns or operates the __________ may also serve as the LRP.
-✓✓LUP
• Sediment basins, at a minimum, shall be designed according to the CASQA
Construction BMP Guidance Handbook. -✓✓True
• In the RUSLE equation, "P" stands for -✓✓Management operations and support
practices.
• Management operations and support practices. -✓✓Management operations and
support practices.
• When does risk level one has to sample? -✓✓When required for non-visible pollutants.
• ATS instruments shall record which of the following? -✓✓Flow, turbidity, and pH
• Which factor(s) of RUSLE can be based on site-specific analysis rather than maps? -
✓✓K and LS
• Failure to obtain coverage under the permit for storm water discharges to waters of the
US is a violation of the -✓✓Clean Water Act and California Water Code
• For traditional construction projects the LRP may be -✓✓The person who possesses
real properly interest in the land upon which the construction activities will occur for the
regulated site
• What does NTU measure? -✓✓a measurement of optical properties of a liquid that
cause light rays to be scattered and absorbed rather than transmitted in straight lines
through a sample.
• Inspection Records have to be kept until the project is complete or three years,
whichever comes first. -✓✓False
• Which factor(s) of RUSLE must be changed to recalculate risk when the construction
duration has changed? -✓✓R
• BMP stands for -✓✓Best Management Practice
, • Do type 1 LUPs typically have a high potential to impact storm quality? -✓✓No
• What does RUSLE stand for? -✓✓Revised Universal Soil Loss Equation
• A discharger must notify the Regional Water Boards if there are planned changes in
the construction activity that -✓✓May result in non-compliance
• A qualifying storm event is -✓✓A rain even that produces 1/2 inch or more of
precipitation with a period of 48 hours or more between rain events.
• Continuous monitoring (no less than 15-min intervals) of ATS is required for: -✓✓
• Rain Event Action Plan must be developed by a QSD -✓✓False
• The CGP allows for not monitoring under what conditions? -✓✓Dangerous weather
conditions, unsafe storm event, and outside of scheduled operations.
• What is the difference between erosion and sedimentation? -✓✓Erosion is the
dislodging and transport of soil and sedimentation is the deposition of material.
• CSMP stands for -✓✓Construction Site Monitoring Program
• What weather forecast would trigger a reap? -✓✓50% chance of rain, within 48 hours.
• During routine inspection a LUP discharger observes a non-stormwater discharge and
therefore must prepare a non storm water report. -✓✓UNSURE* but: False (no non-
stormwater report exists?)
• What BMP does the permit discourage? -✓✓Plastic cover (maybe sediment basin?)
• What factors are used for RUSLE? -✓✓R, K, LS, C, P
• Which two best represent an ATS "mode of operation"? -✓✓Flow through and Batch
treatment
• What does NPDES stand for? -✓✓National Pollutant Discharge Elimination System
• When shall a discharger conduct a construction site evaluation and run-on evaluation?
-✓✓Whenever the results from a storm event daily average indicate that the discharge
is below the lower NAL for pH, exceeds the upper NAL for pH, or exceeds the turbidity
NAL.