Acquisition Strategy Development Questions
With Correct Answers
Using the Standard Capability Maturity Model Integration Appraisal Method for
| | | | | | | | | |
Process Improvement (SCAMPI), an organization whose acquisition processes are
| | | | | | | | |
well documented and standardized would be rated at least: - CORRECT
| | | | | | | | | | |
ANSWER✔✔--Level 1 |
-Level 2 |
-*Level 3* |
-Level 4 |
When selecting a software developer, which of the following should contractors
| | | | | | | | | | |
possess (Select all that apply)? - CORRECT ANSWER✔✔--*Successful past
| | | | | | | | |
performance record* |
-*Domain experience in developing comparable software systems*
| | | | | |
-Maturity level four | |
-*Demonstrable mature software development capability and processes*
| | | | | |
With regard to exceptions to the full funding policy, _________ funds are
| | | | | | | | | | | |
budgeted as a separate procurement line item from the related end item. -
| | | | | | | | | | | | |
CORRECT ANSWER✔✔--Multiyear Procurement
| |
-Incremental
-*Advance Procurement* |
, -Low Rate Initial Production (LRIP)
| | | |
Earned value management (EVM) reports are available to help the program
| | | | | | | | | | |
manager (PM) track the contractor's cost, schedule, and performance against a
| | | | | | | | | | |
Performance Measurement Baseline. - CORRECT ANSWER✔✔--*True* | | | | |
-False
In the Planning, Programming, Budgeting and Execution (PPBE) process, one
| | | | | | | | | |
result of the programming activities is the __________ - CORRECT ANSWER✔✔--
| | | | | | | | | |
Future Years Development Program (FYDP)
| | | |
-Budget Estimate Submission (BES)| | |
-Defense Planning Guidance (DPG) | | |
-*Program Objectives Memorandum (POM)* | | |
If a contractor chooses to use their own quality system, they must demonstrate
| | | | | | | | | | | | |
compliance with the established military standard through formal third party
| | | | | | | | | |
certification. - CORRECT ANSWER✔✔--True | | |
-*False*
The Contracting Officer's responsibilities include all of the following EXCEPT -
| | | | | | | | | | |
CORRECT ANSWER✔✔--Preparing the request for proposal
| | | | |
-*Managing performance of the contractor on a daily basis* | | | | | | | |
-Conducting discussions with potential offerors in response to a solicitation
| | | | | | | | |
-Making a modification to an existing contract
| | | | | |