There are four basic techniques used by the DoD for creating cost estimates:
| | | | | | | | | | | | |
Analogy, Parametric, and Actual Costs are three techniques. - CORRECT
| | | | | | | | | |
ANSWER✔✔-Engineering
Which appropriation category would fund the design of new equipment, material,
| | | | | | | | | |
or software? - CORRECT ANSWER✔✔-Research, Development, Test and
| | | | | | | | |
Evaluation
What's the primary purpose of an Analysis of Alternatives (AoA)? - CORRECT
| | | | | | | | | | | |
ANSWER✔✔-Provide decision-making aid in selecting a cost-effective material
| | | | | | | |
alternative
When comparing alternative concepts to provide needed warfighting capabilities,
| | | | | | | | |
which of the following must be met? - CORRECT ANSWER✔✔-Thresholds
| | | | | | | | |
Estimating potential demand for a capability and developing a rough order of
| | | | | | | | | | | |
magnitude (ROM) estimate of future sales are characteristics of which
| | | | | | | | | |
International Acquisition & Exportability (IA&E) Assessment area? - CORRECT
| | | | | | | | |
ANSWER✔✔-International Markets |
Both the Army and Marine Corps have a capability need to procure additional
| | | | | | | | | | | | |
helicopters beyond the number specified in the current contract; the helicopter
| | | | | | | | | | |
, program is currently in production. What cost estimating technique would the
| | | | | | | | | | |
services most likely use as a basis requesting the funding to pay for the additional
| | | | | | | | | | | | | |
aircraft? - CORRECT ANSWER✔✔-Actual Cost
| | | | |
The largest amount of software life cycle cost comes during the design
| | | | | | | | | | | |
development - CORRECT ANSWER✔✔-False | | |
An AOA is a study of the _________ - CORRECT ANSWER✔✔-Potential Acquisition
| | | | | | | | | | |
Strategies for the alternatives WRONG
| | | | |
Which of the following guidance documents requires DoD Components to
| | | | | | | | | |
incorporate interoperability and defense exportability aspects into Joint
| | | | | | | |
Capabilities Integration and Development System requirements documents to
| | | | | | | |
ensure they are addressed in initial planning and design? - CORRECT
| | | | | | | | | | |
ANSWER✔✔-DFARS
Which of the following are characteristics of ICPs - CORRECT ANSWER✔✔-Shared
| | | | | | | | | | |
cost, Shared risks and benefits, and Government-to-Government
| | | | | |
To obtain guidance and (if required) approvals on the level and type of protection
| | | | | | | | | | | | |
|required, the DoD Component International Program Organization and Program
| | | | | | | | |
Management Offices (PMOs) must engage: - CORRECT ANSWER✔✔-TSFD | | | | | | | |
technology area ("pipe") owners/authorities | | |
In certain situations, there may be a U.S. Government requirements to restrict
| | | | | | | | | | | |
specific portions of a weapon system sale to FMS only while permitting other
| | | | | | | | | | | | |
portions to be acquired DCS - CORRECT ANSWER✔✔-True
| | | | | | |
CORRECT ANSWERS
There are four basic techniques used by the DoD for creating cost estimates:
| | | | | | | | | | | | |
Analogy, Parametric, and Actual Costs are three techniques. - CORRECT
| | | | | | | | | |
ANSWER✔✔-Engineering
Which appropriation category would fund the design of new equipment, material,
| | | | | | | | | |
or software? - CORRECT ANSWER✔✔-Research, Development, Test and
| | | | | | | | |
Evaluation
What's the primary purpose of an Analysis of Alternatives (AoA)? - CORRECT
| | | | | | | | | | | |
ANSWER✔✔-Provide decision-making aid in selecting a cost-effective material
| | | | | | | |
alternative
When comparing alternative concepts to provide needed warfighting capabilities,
| | | | | | | | |
which of the following must be met? - CORRECT ANSWER✔✔-Thresholds
| | | | | | | | |
Estimating potential demand for a capability and developing a rough order of
| | | | | | | | | | | |
magnitude (ROM) estimate of future sales are characteristics of which
| | | | | | | | | |
International Acquisition & Exportability (IA&E) Assessment area? - CORRECT
| | | | | | | | |
ANSWER✔✔-International Markets |
Both the Army and Marine Corps have a capability need to procure additional
| | | | | | | | | | | | |
helicopters beyond the number specified in the current contract; the helicopter
| | | | | | | | | | |
, program is currently in production. What cost estimating technique would the
| | | | | | | | | | |
services most likely use as a basis requesting the funding to pay for the additional
| | | | | | | | | | | | | |
aircraft? - CORRECT ANSWER✔✔-Actual Cost
| | | | |
The largest amount of software life cycle cost comes during the design
| | | | | | | | | | | |
development - CORRECT ANSWER✔✔-False | | |
An AOA is a study of the _________ - CORRECT ANSWER✔✔-Potential Acquisition
| | | | | | | | | | |
Strategies for the alternatives WRONG
| | | | |
Which of the following guidance documents requires DoD Components to
| | | | | | | | | |
incorporate interoperability and defense exportability aspects into Joint
| | | | | | | |
Capabilities Integration and Development System requirements documents to
| | | | | | | |
ensure they are addressed in initial planning and design? - CORRECT
| | | | | | | | | | |
ANSWER✔✔-DFARS
Which of the following are characteristics of ICPs - CORRECT ANSWER✔✔-Shared
| | | | | | | | | | |
cost, Shared risks and benefits, and Government-to-Government
| | | | | |
To obtain guidance and (if required) approvals on the level and type of protection
| | | | | | | | | | | | |
|required, the DoD Component International Program Organization and Program
| | | | | | | | |
Management Offices (PMOs) must engage: - CORRECT ANSWER✔✔-TSFD | | | | | | | |
technology area ("pipe") owners/authorities | | |
In certain situations, there may be a U.S. Government requirements to restrict
| | | | | | | | | | | |
specific portions of a weapon system sale to FMS only while permitting other
| | | | | | | | | | | | |
portions to be acquired DCS - CORRECT ANSWER✔✔-True
| | | | | | |