A manual fire alarm system is required in a Business Group B building
when the combined load of all floors is __________ or more persons.
ANS >> 500
What is the minimum ceiling height in habitable places? ANS >> 7'6"
Exterior walls are required to be fire rated on both sides when their fire
separation distance is less than of equal to ______ feet. ANS >> 10
Feet
When is a building permit not required? ANS >> Building a plastic
covered greenhouse
, CSL PREP SET EXAM
For an occupancy load of less than 50, what is the minimum width of
corridors? ANS >> 36 inches
A building 4 stories high, is greater than 30 feet from the closest
building, equipped with an automatic sprinkler system, and constructed
with 2 hour rated exterior bearing walls and an un-rated wood floor
system, housing a bank shall be classified as what type of construction?
ANS >> IIIB
A building of type IIB construction is equipped with an automatic
sprinkler system. If it houses a restaurant, what is the maximum
allowable number of stories and height? ANS >> 3 Stories
Gypsum Board inspections are required when_____________________
ANS >> The gypsum board is in place, before taping and finishing
Based upon high hazard occupancy, flammable gasses are defined
as_____ ANS >> Physical Hazards
A lecture hall's maximum allowable height in a type IIB construction
high school is_____ ANS >> 55 Feet
What is the minimum height of a guard on the top floor of a structure
occupied for parking motor vehicles? ANS >> 42 inches