The General Contractor is responsible for selecting the means and methods of
construction.
Give this one a try later!
True
, Ambiguities in the contract that cannot be resolved with the standard rules of
contract interpretation are subject to contra proferentum which dictates that
interpretations will be held against the drafter. However, according to the ___________, the
bidder may be held liable for any additional costs accrued due to an obvious
discrepancy if they fail to notify the owner before performing the work.
Give this one a try later!
Patent ambiguity rule
__________ are additions or corrections to the drawings or specifications that are issued
before the construction contract is executed.
Give this one a try later!
Addenda
attractive feature of Standard Contract Forms is that they are widely accepted within
the industry and are well-suited to projects of varying types and scales. Because no
two projects are identical, differences in project requirements must be addressed
within the contract. The conditions related to the unique requirements of a particular
project are typically formed in which contract document?
Give this one a try later!
Special condition
construction.
Give this one a try later!
True
, Ambiguities in the contract that cannot be resolved with the standard rules of
contract interpretation are subject to contra proferentum which dictates that
interpretations will be held against the drafter. However, according to the ___________, the
bidder may be held liable for any additional costs accrued due to an obvious
discrepancy if they fail to notify the owner before performing the work.
Give this one a try later!
Patent ambiguity rule
__________ are additions or corrections to the drawings or specifications that are issued
before the construction contract is executed.
Give this one a try later!
Addenda
attractive feature of Standard Contract Forms is that they are widely accepted within
the industry and are well-suited to projects of varying types and scales. Because no
two projects are identical, differences in project requirements must be addressed
within the contract. The conditions related to the unique requirements of a particular
project are typically formed in which contract document?
Give this one a try later!
Special condition