Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

LOUISIANA BUSINESS AND LAW EXAM QUESTIONS WITH CORRECT SOLUTIONS||100% GUARANTEED PASS||UPDATED 2026/2027 SYLLABUS||ALREADY GRADED A+||RECENT VERSION

Beoordeling
-
Verkocht
-
Pagina's
17
Cijfer
A+
Geüpload op
10-05-2026
Geschreven in
2025/2026

LOUISIANA BUSINESS AND LAW EXAM QUESTIONS WITH CORRECT SOLUTIONS||100% GUARANTEED PASS||UPDATED 2026/2027 SYLLABUS||ALREADY GRADED A+||RECENT VERSION When the project is nearing completion, a ________________is created during a walkthrough to determine any details that still need to be addressed in order to fully complete the project. - ANSWER punch list For a small construction company, who would typically be the project manager? - ANSWER prime contractor (general contractor) What are the steps involved the closing out each project? - ANSWER Onsite walk-through to develop a punch list Contractor provides certificate Owner makes final payment All of the above In order for a contract to become a binding document, it must contain four key elements which are an offer and acceptance, competent parties, legal purpose and: - ANSWER Consideration The term consideration means that both parties to a contract must be exchanging something of value - ANSWER true What is the term used to identify changes made to contract documents before the execution of the basic owner contractor agreement? - ANSWER Addenda Oral contracts are valid, but are often difficult to enforce. - ANSWER true Terms used in a contract that allow the owner to withhold an agreed upon percentage of the contract funds until the project is 100% complete is called: - ANSWER Retainage Losses paid by the contractor if the project isn't completed in a specified time frame written into the contract are called: - ANSWER liquidated damages Changes made to the contract documents after the signing of the basic owner contractor agreement are called: - ANSWER Modifications Change orders are an example of contract modifications. - ANSWER true When one contractor assumes all design and construction responsibilities this contract is known as: - ANSWER Design/Build The most important thing for both the contractor and the owner to do before signing a contract is to read and understand the contract. - ANSWER true A contractor is submitting a progress payment request on a $357,000 contract. The contractor has previously been paid $110,000 and the owner has a 10% retainage agreement. The project is now 50% complete. How much should the contractor expect to receive after retainage is applied to the net billing? - ANSWER $61,650 What type of contract provides the owner with the total price for the project in advance? - ANSWER Lump sum The contractor and the owner agree to set aside a sum of money for electrical fixtures and plumbing fixtures in the contract budget because the actual cost of these items are unknown. The set aside money is called: - ANSWER Allowance If the contract specifications require 5/8" OSB to sheath the roof and the contractor used 1/2" OSB to save money, the contractor could be sued for breach of contract. - ANSWER true If changes to the original contract occur, it is important to write a "Change Order" and have all parties on the contract sign it before the actual changes are made. - ANSWER true The first and most important element in a contract is offer and acceptance. - ANSWER true If a contractor finds a handwritten provision on a drawing, he should ignore it and proceed as it was originally directed by the original printed instruction. - ANSWER false

Meer zien Lees minder
Instelling
LOUISIANA BUSINESS AND LAW
Vak
LOUISIANA BUSINESS AND LAW

Voorbeeld van de inhoud

LOUISIANA BUSINESS AND LAW
EXAM QUESTIONS WITH CORRECT
SOLUTIONS||100% GUARANTEED
PASS||UPDATED 2026/2027
SYLLABUS||ALREADY GRADED
A+||<<RECENT VERSION>>
When the project is nearing completion, a ________________is created during a
walkthrough to determine any details that still need to be addressed in order to
fully complete the project. - ANSWER ✓ punch list

For a small construction company, who would typically be the project manager? -
ANSWER ✓ prime contractor (general contractor)

What are the steps involved the closing out each project? - ANSWER ✓ Onsite
walk-through to develop a punch list

Contractor provides certificate

Owner makes final payment

All of the above

In order for a contract to become a binding document, it must contain four key
elements which are an offer and acceptance, competent parties, legal purpose and:
- ANSWER ✓ Consideration

The term consideration means that both parties to a contract must be exchanging
something of value - ANSWER ✓ true

What is the term used to identify changes made to contract documents before the
execution of the basic owner contractor agreement? - ANSWER ✓ Addenda

,Oral contracts are valid, but are often difficult to enforce. - ANSWER ✓ true

Terms used in a contract that allow the owner to withhold an agreed upon
percentage of the contract funds until the project is 100% complete is called: -
ANSWER ✓ Retainage

Losses paid by the contractor if the project isn't completed in a specified time
frame written into the contract are called: - ANSWER ✓ liquidated damages

Changes made to the contract documents after the signing of the basic owner-
contractor agreement are called: - ANSWER ✓ Modifications

Change orders are an example of contract modifications. - ANSWER ✓ true

When one contractor assumes all design and construction responsibilities this
contract is known as: - ANSWER ✓ Design/Build

The most important thing for both the contractor and the owner to do before
signing a contract is to read and understand the contract. - ANSWER ✓ true

A contractor is submitting a progress payment request on a $357,000 contract. The
contractor has previously been paid $110,000 and the owner has a 10% retainage
agreement. The project is now 50% complete. How much should the contractor
expect to receive after retainage is applied to the net billing? - ANSWER ✓
$61,650

What type of contract provides the owner with the total price for the project in
advance? - ANSWER ✓ Lump sum

The contractor and the owner agree to set aside a sum of money for electrical
fixtures and plumbing fixtures in the contract budget because the actual cost of
these items are unknown. The set aside money is called: - ANSWER ✓ Allowance

If the contract specifications require 5/8" OSB to sheath the roof and the
contractor used 1/2" OSB to save money, the contractor could be sued for breach
of contract. - ANSWER ✓ true

, If changes to the original contract occur, it is important to write a "Change Order"
and have all parties on the contract sign it before the actual changes are made. -
ANSWER ✓ true

The first and most important element in a contract is offer and acceptance. -
ANSWER ✓ true

If a contractor finds a handwritten provision on a drawing, he should ignore it and
proceed as it was originally directed by the original printed instruction. -
ANSWER ✓ false

Retainage is usually paid with the final payment. - ANSWER ✓ true

The contract should provide for a schedule as to when progress payments will be
disbursed and the amount of money that will be available to the contractor at each
payment. - ANSWER ✓ true

A ____________ is when the terms of the contract have been violated to the
extent that the contract can no longer be valid. - ANSWER ✓ material breach

What type of insurance will protect the contractor for losses due to a fire on his
construction project? - ANSWER ✓ All Risk Builders insurance

General liability insurance will protect the contractor against claims brought by
third parties who are not employed by the contractor. - ANSWER ✓ true

Who pays for workers' compensation insurance? - ANSWER ✓ the employer

A guarantee that a contractor will pay certain subcontractors, laborers, and
material suppliers associated with the project would be known as a________ -
ANSWER ✓ payment bond

Any monies paid out by a surety company will need to be paid back. - ANSWER
✓ true

Equipment in transit, on the premises or at the job site, would typically be covered
by: - ANSWER ✓ Equipment floater policy

Geschreven voor

Instelling
LOUISIANA BUSINESS AND LAW
Vak
LOUISIANA BUSINESS AND LAW

Documentinformatie

Geüpload op
10 mei 2026
Aantal pagina's
17
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$15.09
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
SmartscoreAaron Chicago State University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
79
Lid sinds
1 jaar
Aantal volgers
6
Documenten
4078
Laatst verkocht
22 uur geleden
SMARTSCORES LIBRARY

Get top-tier academic support for Psychology, Nursing, Business, Engineering, HRM, Math, and more. Our team of professional tutors delivers high-quality homework, quiz, and exam assistance—ensuring scholarly excellence and grade-boosting results. Trust our collaborative expertise to help you succeed in any course at U.S.A Institutions.

3.1

7 beoordelingen

5
3
4
1
3
0
2
0
1
3

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen