(PMP) Practice Exam Questions And
Correct Answers (Verified Answers) Plus
Rationales 2026 Q&A Instant Download
Q1. Which document authorizes the existence of a project and provides the
project manager authority?
A. Project Schedule
B. Project Charter
C. Risk Register
D. Scope Statement
Answer: Project Charter
Rationale: The project charter formally authorizes the project and grants the
project manager authority to apply organizational resources.
Q2. What is the primary purpose of a Work Breakdown Structure (WBS)?
A. Assign project team members
B. Define project risks
C. Decompose deliverables into manageable components
D. Estimate project costs
Answer: Decompose deliverables into manageable components
,Rationale: The WBS breaks down project scope into smaller, manageable work
packages.
Q3. Which process group includes defining and refining project objectives?
A. Initiating
B. Planning
C. Executing
D. Closing
Answer: Planning
Rationale: Planning involves establishing scope, objectives, and detailed plans
for execution.
Q4. What is the critical path in project management?
A. The most expensive tasks
B. The longest sequence of dependent activities
C. The shortest path through the project
D. Tasks with no slack
Answer: The longest sequence of dependent activities
Rationale: The critical path determines the minimum project duration based on
dependent tasks.
Q5. Which tool is used to identify risks in a project?
A. RACI Matrix
B. Risk Register
C. Gantt Chart
D. Pareto Chart
Answer: Risk Register
Rationale: The risk register documents identified risks, responses, and owners.
, Q6. What is scope creep?
A. Approved changes to scope
B. Uncontrolled expansion of project scope
C. Risk mitigation strategy
D. Schedule compression technique
Answer: Uncontrolled expansion of project scope
Rationale: Scope creep refers to uncontrolled changes without proper approval.
Q7. Which technique is used for conflict resolution by finding a middle ground?
A. Avoiding
B. Smoothing
C. Compromising
D. Forcing
Answer: Compromising
Rationale: Compromising involves each party giving up something to reach
agreement.
Q8. What is the main purpose of stakeholder analysis?
A. Assign tasks
B. Identify communication methods
C. Determine stakeholder expectations and influence
D. Estimate budget
Answer: Determine stakeholder expectations and influence
Rationale: Stakeholder analysis helps manage expectations and engagement
strategies.
Q9. Which process involves formal acceptance of project deliverables?
A. Executing
B. Monitoring
C. Closing