CORRECT ANSWERS GRADED A+
LATEST 100% GUARANTEED PASS
Trust, Flexibility - CORRECT ANSWER-Successful Design Build requires _____ & _______
between participants
Hammurabi - CORRECT ANSWER-Singular responsibility for both design & construction was first
codified by ____
Bridging Documents - CORRECT ANSWER-Owner provided items such as 20% design or more
and provides prescriptive specs at RFP.
Spearin Doctrine - CORRECT ANSWER-Owner is responsible for implied warranties in the
sufficiency of the specifications.
Performance Requirements - CORRECT ANSWER-____ ____ should identify end results.
Design Build - CORRECT ANSWER-Single point of responsibility for both design & construction is
an attribute of what delivery method?
, Substantiation - CORRECT ANSWER-The process of checking milestones along the way for
completeness.
Prescriptive - CORRECT ANSWER-Owner requiring specific products or methods be instituted by
DB team in order to achieve desired performance.
False - CORRECT ANSWER-T/F Detailed estimating is the Building systems approach to
estimating
False - CORRECT ANSWER-T/F feasibility estimate is cost model and establishes budget for
project
True - CORRECT ANSWER-T/F key element of quality assurance is keeping communication lines
open between owner and DB
True - CORRECT ANSWER-T/F in Design/cost relationship of DB, the constructor establishes
design parameters for architect
False - CORRECT ANSWER-T/F trust is most important thing for DB
Schematic estimating - CORRECT ANSWER-DB estimating sequence where 15%-20% of design is
completed
Trend logs - CORRECT ANSWER-Provides baseline budgets and schedules and list estimate
trends
Committed Design - CORRECT ANSWER-Drawings and specs are approved by DOR and
confirmed within budget