Certain non-storm water discharges may be necessary for the completion of
construction projects. Therefore the General Permit authorizes such discharges
provided they meet the following conditions except:
a. Meet the NALs for pH and turbidity
b. Not cause or contribute to a violation of water quality standards
c. Comply with BMPs as described in the SWPPP
d. Be infeasible to eliminate
e. Causes or threatens to cause pollution, contamination, or nuisance - ANSWER:
e. Causes or threatens to cause pollution, contamination, or nuisance
Hydrologic source controls are a design technique that minimize and/or slow the
rate of stormwater runoff from the site. Examples include:
a. Reduction of pervious surfaces
b. Use of landscaping as a storm drain treatment feature
c. Drain rooftop downspouts to impervious areas
d. Stormwater treatment facility - ANSWER: b. Use of landscaping as a storm
drain treatment feature
If the R Factor is , you can apply for the Erosivity Waiver.
,2|Page
a. 1
b. Less than 1
c. 5
d. Less than 5 - ANSWER: d. Less than 5
NEL Violation Reports must be submitted to State Board within 24 hours after
exceedance has been identified. NEL's are only subject to:
a. Risk Level 1
b. Risk Level 2
c. Risk Level 3
d. ATS Sites only - ANSWER: d. ATS Sites only
A likely precipitation event is any weather pattern that is forecasted to have a
% or greater probability of producing precipitation in the project area.
a. 10
b. 25
c. 50
d. 75
e. 99 - ANSWER: C
A QSP is responsible for:
a. Day to day implementation, inspections, and observations
b. Amending the SWPPP as required
,3|Page
c. Developing and certifying the SWPPP
d. Certifying reports in SMARTS - ANSWER: a. Day to day implementation,
inspections, and observations
A storm that produces ½ inch or more of precipitation, with a 48 hour or greater
period between rain events is a/an...
a. Qualifying rain event
b. Extended storm event
c. Inactive storm event
d. Unsafe monitoring event - ANSWER: a. Qualifying rain event
A temporary or permanent structural BMP that directs concentrated flows away
from disturbed areas and prevents erosion is...
a. erosion control
b. run on/ run off control
c. sediment control - ANSWER: b. run on/ run off control
Acceptable methods to demonstrate final stabilization include:
a. 50%vegetative coverage
b. 100% vegetative coverage
c. RUSLE 2 method - ANSWER: c. RUSLE 2 method
Activities under the CGP include:
, 4|Page
a. Routine maintenance to maintain original line and grade, hydraulic capacity, or
original purpose of the facility.
b. Disturbances to land surfaces solely related to agricultural operations.
c. Clearing and grading 2 acres of land
d. Discharges of storm water from areas on tribal lands. - ANSWER: c. Clearing
and grading 2 acres of land
All NAL data must be uploaded within after NAL exceedance has been
identified
a. 24 hours
b. 1 week
c. 10 days
d. 2 weeks - ANSWER: c. 10 days
Once identified, dischargers shall begin implementing repairs or design changes to
BMPs:
a. Immediately
b. Within 24 hours
c. Within 48 hours
d. ASAP, but not more than 72 hours - ANSWER: d. ASAP, but not more than 72
hours