Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

GMS450 Final Exam UPDATED QUESTIONS AND CORRECT ANSWERS

Beoordeling
-
Verkocht
-
Pagina's
28
Cijfer
A+
Geüpload op
14-05-2026
Geschreven in
2025/2026

GMS450 Final Exam UPDATED QUESTIONS AND CORRECT ANSWERS Project Crashing - CORRECT ANSWER overall project completion time. Normal Time - CORRECT ANSWER conditions. Normal Cost - CORRECT ANSWER Crash Time - CORRECT ANSWER Crash Cost - CORRECT ANSWER Cost to Crash/Period - CORRECT ANSWER Shortening some activities within a project to reduce The time necessary to complete an activity under normal The activity cost associated with the normal time. The shortest possible time to complete an activity. The activity cost associated with the crash time. =(CC-NC)/(NT-CT) Which Activities Should Be Crashed? - CORRECT ANSWER One or more of the activities in the critical path should be chosen to crash. The activity with the lowest cost to the firm should be crashed. Resource Leveling - CORRECT ANSWER - When the project is large and contains many resource over-allocations, resource leveling must be accomplished. - It is a technique in which start and finish dates are adjusted based on resource constraints w/ the goal of balancing demand for resources w/ the available supply. - Purpose: to create a smoother distribution of resource usage. - Aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. - Done by delaying or splitting tasks until the resources assigned to them are no longer over distributed. Activity Slack - CORRECT ANSWER Formula: S = LF - EF or LS - ES

Meer zien Lees minder
Instelling
GMS450
Vak
GMS450

Voorbeeld van de inhoud

GMS450 Final Exam UPDATED
QUESTIONS AND CORRECT ANSWERS
Project Crashing - CORRECT ANSWER Shortening some activities within a project to reduce
overall project completion time.



Normal Time - CORRECT ANSWER The time necessary to complete an activity under normal
conditions.



Normal Cost - CORRECT ANSWER The activity cost associated with the normal time.



Crash Time - CORRECT ANSWER The shortest possible time to complete an activity.



Crash Cost - CORRECT ANSWER The activity cost associated with the crash time.



Cost to Crash/Period - CORRECT ANSWER =(CC-NC)/(NT-CT)



Which Activities Should Be Crashed? - CORRECT ANSWER One or more of the activities in
the critical path should be chosen to crash. The activity with the lowest cost to the firm should be
crashed.



Resource Leveling - CORRECT ANSWER - When the project is large and contains many
resource over-allocations, resource leveling must be accomplished.

- It is a technique in which start and finish dates are adjusted based on resource constraints w/ the goal
of balancing demand for resources w/ the available supply.

- Purpose: to create a smoother distribution of resource usage.

- Aims to minimize the period-by-period variations in resource loading by shifting tasks within their
slack allowances.

- Done by delaying or splitting tasks until the resources assigned to them are no longer over-
distributed.



Activity Slack - CORRECT ANSWER Formula: S = LF - EF or LS - ES

,Pseudoactivities - CORRECT ANSWER - Several projects can be linked together w/
pseudoactivities.

- They have duration, but require no resources.

- They allow a set of projects to be linked and dealt w/ as though it were a single project.

- Individual projects are interrelated by specifying predecessor/successor relationships.



Criteria of Priority Rules - CORRECT ANSWER 1. Schedule slippage: the amount project or
set of projects delayed by the application of a leveling rule. The PM must trade off penalty costs or
displeasure of clients against the cost of adding resources.

2. Resource utilization: the extent to which resources are over or under worked.

3. In-process inventory: amount of unfinished work in the system.

* The min. slack rule is the best overall priority rule according to research, giving the best combo. of
minimum project slippage, minimum resource idle-time and minimum in-process inventory.



Problems w/ Traditional Project Management - CORRECT ANSWER - Additional safety time
should be implemented beyond the work content time required to be embedded within the task
duration to increase the probability and high-confidence that the task will be completed on time.

Problems include:

- Not starting task until the last moment

- Delaying completion of task



Goldratt's Critical Chain - CORRECT ANSWER - Eli Goldratt created critical chain project
mgmt. in response to many projects being dogged by performance manifested in:

1) Longer than expected duration

2) Frequently missed deadlines

3) Increased costs in excess of budget

4) Substantially less deliverables than originally promised



Multitasking - CORRECT ANSWER - Assigning team members to multiple projects and
having them allocate their time across these projects.

- Typically a penalty or cost associated w/ switching from working on one project to another (usually
extends activity times)

, Goldratt's Solution - CORRECT ANSWER - Suggests that the key to resolving this is to
schedule the start of new projects based on the availability of bottleneck resources

- Suggests time buffers between bottleneck resource and resources that feed it.

* A bottleneck (or constraint) in a supply chain means the resource that requires the longest time in
operations of the supply chain for certain demand.



Two Potential Sources That Can Delay the Project - CORRECT ANSWER 1) Delay in the tasks
that make up the critical chain.

2) Delay in activity feeding the critical chain that results in delay of the critical chain.



Project Buffer - CORRECT ANSWER - A project buffer is inserted at the end of the project
network between the last task and the completion date

- Any delays on the longest chain of dependent tasks will consume some of the buffer but will leave
the completion date unchanged and protect the project.



Feeding Buffer - CORRECT ANSWER - Delays on paths of tasks feeding into the longest
chain can impact the project by delaying a subsequent task on the critical chain.

- The feeding buffer is typically recommended to be half the size of the safety time taken out of the
feeding path.



Project Risk - CORRECT ANSWER - Definition: an uncertain event or condition that, if it
occurs, has a positive or negative effect on at least one project objective.

- Projects are all about uncertainty. Uncertainty cannot be eliminated, however, it can be minimized
with effective PM



Risk Management - CORRECT ANSWER - Process of identifying, analyzing and responding
to project risk in order to maximize positive outcomes.



Risk Mgmt. Breakdown Into Sub-Processes - CORRECT ANSWER 1. Risk management
planning

2. Risk identification

3. Qualitative risk analysis

4. Quantitative risk analysis

Geschreven voor

Instelling
GMS450
Vak
GMS450

Documentinformatie

Geüpload op
14 mei 2026
Aantal pagina's
28
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$11.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
STANFORDTOPGRADES Stanford University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
56
Lid sinds
1 jaar
Aantal volgers
2
Documenten
7115
Laatst verkocht
1 dag geleden
TOPSELLER

Hi there! I'm dedicated to sharing my high-quality study guides and helpful EXAM Materials to make your learning easier and more efficient. All my materials are well-organized and tailored to help you ace your courses. I offer genuine and dependable exam papers that are directly obtained from well-known, reputable institutions as a highly regarded professional who specializes in sourcing study materials. Kindly don't hesitate to contact me, my study guides, notes and exams or test banks, are 100% graded and fully guaranteed

Lees meer Lees minder
3.8

8 beoordelingen

5
3
4
1
3
3
2
1
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen