1. The windows manufacturer's catalog will contain a sizing table with what
measurements - Correct Answer: Masonry opening, rough opening,
frame size, glass size, and occasionally sash size
2. What are the framing members which establish a rough floor opening -
Correct Answer: Trimmers, headers and tail joist
3. Gutter splash blocks should be at least how long - Correct Answer: 3'
long
4. What is the most common type of copper piping used in residential homes -
Correct Answer: Type M with Red Ink
5. When installing steel joist tracks the minimum length of a track splice is
______? - Correct Answer: 6"
,6. How many straps are necessary to attach a gutter downspout - Correct
Answer: 2 Straps
7. The measure of a materials ability to resist heat transmission? - Correct
Answer: R Value
8. The unit run measurement for a rafter that is attached to the ridge at a 45
degree angle is? - Correct Answer: 17"
9. What source should the contractor use to determine the required rough-in
information of aluminum clad wood windows? - Correct Answer:
Manufacturers data
10.The unit run measurement for a rafter that is attached to the ridge at a 90
degree angle is? - Correct Answer: 12"
11.What is the minimum recommended overlap for plain bevel wood siding? -
Correct Answer: 1"
12.What is the minimum size breaker for an electric furnace? - Correct
Answer: 30 Amps
13.If the sheet of plywood has a 32/16 panel identification index, it may be
used as a roof decking with a maximum span of? - Correct Answer: 32"
,14.When a contractor is installing a Oak floor what should be done after the
subflooring has been cleaned? - Correct Answer: Install 15lb felt with
over laps
15.How long should the screws be to fasten 3/4" thick cabinets to studs
covered with 1/2" drywall? - Correct Answer: 2 1/4"
16.When installing three tab shingles, no nails should be placed within how
many inches of a valley? - Correct Answer: 6"
17.What temperature should the building be when installing wood floors? -
Correct Answer: 70 degrees
18.When installing roof sheathing nail spacing at the edge of the panel should
be spaced? - Correct Answer: 6"
19.Which tool measures horizontal angles only? - Correct Answer: Builders
or dumpy level
20.Drywall that is used in bathrooms or high moisture areas? - Correct
Answer: MR (Green Board)
21.MDF panels should not be butted tightly and aligned with a recommended
gap of ________? - Correct Answer: 1/16"
, 22.What angle does the valley rafter form with the main ridge board in a roof
of uniform pitch? - Correct Answer: 45 degrees
23.When surveying, 2 degrees of measurement would equal? - Correct
Answer: 120 Minutes
24.Nail pops are greatly reduced if the moisture content of the framing is less
than ____ at the time the drywall is installed? - Correct Answer: 19%
25.Subfloor plywood underlayment spacing is: - Correct Answer: 1/8" on
ends and sides
26.What is the common thickness of load bearing walls - Correct Answer:
18G and 29G
27.What is the door hinge size for a 1 3/8" interior door? - Correct Answer:
3 1/2" x 3 1/2"
28.What is the minimum distance batter boards can be placed from the point
of excavation? - Correct Answer: 4'
29.What is the typical maximum distance between a gutter's high point and
the downspout? - Correct Answer: 25'