Answers with Complete A+ Solutions 100% Correct!!!
"A prime contractor has complied with all but two of the small business participation
requirements in its small business participation commitment document
( SBPCD). The prime contractor recently sent you a corrective action plan that details the
practical efforts the prime contractor will take to meet these two
requirements. You are assessing the prime contractor's pertonnance in the Small Business
Subcontracting Section of the Contractor Pertormance Assessment
Reporting System (CPARS). What will you do now? To answer this question. feel free to refer
to FAR 42.1502. Table 42 2. Evaluation Rating Definitions. (Select two
that apply.)" - correct answer -"Include an objective. detailed narrative thal explains and
supports lhe evaluation rating you assign.
When assessing the prime contracto(s performance. consider if ii made a good faith effort
to meet ils small business subcontracting goals and requirements.
"
"The Contractor Purchasing System Review (CPSR) Team completed its review of a p rime
contractor's system for subcontracting. The Team found that the prime
contractor maintains an organization plan that clearly delineates responsibility and
authority. The Team found that some mandatory flow-down clauses were not
1|Page
,included in applicable subcontracts. The Team found that procedures are in place to ensure
the proper types of subcontracts are selected. The Team found no
evidence that the prime contractor is conducting oversight and surveillance of the s
ubcontractors' efforts. The Team found that the prime contractor consistently
uses competitive sourcing to the maximum extent practicable. including ensuring tllat
subcontracts are not issued to subcontractors that are debarred or
suspended. Based on the CPSR Team's findings and the contractor purchasing system
criteria in DFARS 252.244 7001. how many significant deficie - correct answer -2
"A S20 million cost-plus.fixed-fee contract has been awarded to DEZ. Inc.. for engineering
modifications. The decision was made during pre.award to require
advance notification and consent to subcontract. The procuring contracting officer entered
three subcontractors in Paragraph U) of FAR 52.244-2. Subcontracts. to
include EDI Engineering. LLC. DEZ. Inc.. does not have an approved purchasing system. The
DEZ. Inc.. program manager is asking if she needs to provide advance
notification of intent to award a subcontract to EDI Engineering. LLC. for S4 million. What will
you tell her?" - correct answer -No. because EDI Engineering. LLC. is listed in paragraph 0)
of FAR 52.244-2. therefore. this subcontractor has already been approved during pre-award.
Which of the following are subcontracting plan requirements? (Select three that apply.) -
correct answer -"Subcontracting goals for the socioeconomic categories expressed as a
percentage of total dollars planned to be subcontracted
2|Page
, Assurances the ofieror will make timely payments to its subcontractors
Assurances the offerer will submit periodic reports of its actual progress complying with its
subcontracting plan
"
Which of the following are accurate statements about the DoD Mentor-Protege Program?
(Select th ree that apply.) - correct answer -"The Program's mentors may be incentivized by
receiving credit toward the applicable small business subcontracting goals in their small
business subcontracting plan.
The Program's mentors may be incentivized by DoD through reimbursement of the
development assistance costs they incur helping their proteges.
Government personnel need to monttor the prime contractor's developmental assistance
program to ensure any incentives are property applied.
"
"What is a contract awarded directly by the prime contractor for the purpose of acquiring
supplies or services {including construction) for the performance of a
3|Page