QUESTIONS AND CORRECT ANSWERS
Voltage ride through capability of the plant must be approved by - CORRECT
ANSWER ERCOT
Any resource or customer owned switching device that can interrupt flow 60kV/Greater must have an
agreement with _____ to schedule outages on - CORRECT ANSWER TO
The resource entity representing a Non-Coordinated test must inform ERCOT and the TO ___ hours
prior to the proposed start of the test - CORRECT ANSWER 2
Lagging reactive tests should be performed during __ load periods - CORRECT
ANSWER High
Leading reactive tests should be performed during __ load periods - CORRECT ANSWER Low
The ___ representing a generation resource shall be responsible for scheduling reactive verification
tests when requested by the resource entity - CORRECT ANSWER QSE
Resource entity owners of transmission facilities shall provide to ___ all nominal transmission facility
ratings - CORRECT ANSWER ERCOT
___ must notify ERCOT of any changes in its transmission facility status within ten seconds -
CORRECT ANSWER TO
Each ___ shall have a vegetation management program outlining procedures to prevent transmission
line contact with vegetation - CORRECT ANSWER Transmission Owner
The ERCOT LFC system shall deploy regulation service and __ __ energy service to provide
satisfactory frequency control - CORRECT ANSWER Responsive Reserve