Answers (Grade A+)
When an organization has the resources and a system must be built
from scratch, an organization should choose what type of software?
(ch.2)
-In-house development
-Prepackaged software
-Off the shelf
-Open source -
correct answer ✅In-house development
Which of the following is NOT a major category of sources of
software? (ch.2)
-Offshore
-Cloud computing vendors
-In-house developers
-Package software -
correct answer ✅Offshore
Intuit's QuickBooks is an example of what type of software? (ch.2)
,ISTM 320 Exam 3 Review Questions &
Answers (Grade A+)
-ERP software
-In-house software
-Pre-packaged software
-Open source software -
correct answer ✅Pre-packaged software
Which firm is best known for its ERP software solution? (ch.2)
-SAP AG
-Oracle
-Microsoft
-Google -
correct answer ✅SAP AG
When considering off-the-shelf software, which choice is one of the
most important criteria to consider? (ch.2)
-Vendor support
-Cost
-Flexibility
,ISTM 320 Exam 3 Review Questions &
Answers (Grade A+)
-Response time -
correct answer ✅Vendor support
Which of the following is NOT a part of project initiation? (ch. 4/5)
-Create the project initiation team
-Establish management procedures
-Create a project budget
-Develop the project charter -
correct answer ✅Create a project budget
All of the following are included in the baseline project report
except ________. (ch. 4/5)
-Introduction
-System description
-Feasibility assessment
-Conclusion -
correct answer ✅Conclusion
, ISTM 320 Exam 3 Review Questions &
Answers (Grade A+)
Which group chooses projects that most often reflect the larger
needs of the organization? (ch. 4/5)
-Business unit
-Steering committee
-Functional manager
-Development group -
correct answer ✅Steering committee
If a project is selected, what is the most likely next step? (ch. 4/5)
-The project will begin.
-The project will be funded.
-The project has to be signed off by management.
-The project is no longer considered. -
correct answer ✅The project will be funded.
Which of the following is NOT a source for IS development
requests? (ch. 4/5)