⩥ Who can request a Mechanics Lien?
Answer: Contractor or Sub-Contractor
⩥ How many days do you have to issue a Mechanics Lien
Answer: 180 Days
⩥ How many days do you have to issue a notice of a Mechanics Lien?
Answer: 120 days
⩥ What is the % of value must the property have before you are eligible
to issue a ML?
Answer: 15%
⩥ How many days must you keep records if someone is affected by led
or mold?
Answer: 3 years
, ⩥ How long do you have to notified OSHA if there is death on work
site?
Answer: 8 hours
⩥ How many long do you have to get your license?
Answer: 2 years
⩥ How many years do you have before renewing your license?
Answer: 2 years
⩥ How many people on the commission?
Answer: 9
⩥ What is the commission made up of?
Answer: 4 Tradesman, 1 Banker, 4 Consumers (min 3 Home
improvement) 1-15
⩥ Who appoints the commission?
Answer: The Governor
⩥ What title is the Door to Door Act?
Answer: Title 14