A+ Grade
Clean Water Act
- correct answer 1970s law that set into place the regulation of stormwater
NPDES
- correct answer Requirements for managing stormwater activity on a construction site are outlined in
the following regulation
Immediately after the project award and before the general contractor begins any site work
- correct answer Onsite stormwater pollution prevention plan (SWPPP) binder should be put together by
the general contractor
Flushing a spill down the storm drain
- correct answer Which of the following is not a beneficial use of water
Discharge from contaminated ground water
- correct answer Which of the following is never an allowable stormwater discharge from a construction
site.
All construction activity, inside and outside the building is complete and permanent stabilization has
been verified is adequate to meet permit requirements
- correct answer The notice of termination (NOT) can be filed when
All of the above
- correct answer You should have a SWPPP for construction because
Site Specific
- correct answer A well designed SWPPP should be
, After the SWPPP is prepared and before starting construction
- correct answer The stormwater notice of intent (NOI) must be submitted
All of the above
- correct answer Potential pollutant sources stored on a construction site may include
Seek written approval from the project SWPPP designer and, if required, the project owner
- correct answer If you believe stormwater BMP modifications are necessary, you must
The SWPPP Certification Letter
- correct answer The document is in the SWPPP that certifies a general contractors commitment to
compliance with the SWPPP is
Protects the site by coordinating timing with construction activities and minimizing pollutant exposure
- correct answer Sequencing and scheduling BMP installation
Account for the time it takes to install and/or implement BMPs between each phase of construction
- correct answer Factors to consider when creating your schedule include
Note Locations and dates of installation on the site map
- correct answer When installing BMP controls
SWPPS BMPs and the construction schedule
- correct answer Stormwater issues typically discussed during the stormwater/SWPPP preconstruction
meeting include, among others
downslope of construction areas prior to starting land disturbing activities
- correct answer Sediment control devices must be installed
Appropriate vegetative stabilization
- correct answer When inspecting inlet protection look for all but the following