QUESTIONS AND SOLUTIONS GUARANTEE A+
✔✔Which of the following are coating inspector's responsibilities? (Select all that apply)
A. To advise coating applicators on how to improve their work
B. To ensure you have the required inspection equipment for the project
C. To obtain, read, and understand the project's specification
D. To document and report results
E. To clarify any ambiguities regarding their role - ✔✔B. To ensure you have the
required inspection equipment for the project
C. To obtain, read, and understand the project's specification
D. To document and report results
E. To clarify any ambiguities regarding their role
✔✔According to the CIP attestation, when is it ok for a QA inspector to accept a gift
from a contractor?
A. When the value is under $25.oo
B. If your company policy allows gifts
C. After the job is complete
D. It's never acceptable - ✔✔D. It's never acceptable
✔✔Inspection reports typically provide sufficient detail permitting the owner to evaluate
which of the following? (Select all that apply)
A. Contractor's performance
B. Inspector's performance
C. Job progress
D. Work interruptions - ✔✔A. Contractor's performance
B. Inspector's performance
C. Job progress
D. Work interruptions
✔✔What does a well-written coating Specification do?
A. It guides the contractor with a walk-through of how a project should be completed
B. It provides a clear understanding of what is expected throughout the coating project
C. It focuses exclusively on what is expected of the coating inspector
D. It leaves details open to interpretation so the contractor can save money - ✔✔B. It
provides a clear understanding of what is expected throughout the coating project
✔✔Which action is important for an inspector to take during a pre-job conference?
A. Ask for a clarification regarding any inspection tasks that are unclear in the
specification
B. Schedule a second conference at a later date tp ensure that the team can meet
again
C. Focus the discussion exclusively on what is expected of the coating inspector
, D. Persuade the owner to change the Specification to include less detail to increase
flexibility - ✔✔A. Ask for a clarification regarding any inspection tasks that are unclear in
the specification
✔✔Where would an inspector locate the correct procedure for mixing the specified
coating material?
A. Specification
B. Standard
C. Product Data Sheet
D. Safety Data Sheet - ✔✔C. Product Data Sheet
✔✔A document produced by manufactures that provides valuable information about the
product - ✔✔Product Data Sheet
✔✔Provides information about the hazards a chemical presents and advise on the
safety precautions that should be taken. - ✔✔Safety Data Sheet
✔✔A formal legally enforceable document that tells the contractor what to do and where
to do it, but generally doesn't tell him or her how to do it. - ✔✔Specification
✔✔A formal document produced by key industry bodies that provide guidance for
carrying out technical procedures. - ✔✔Standard
✔✔A quality control toll, developed from the guiding documents that help inspectors to
ensure that all specified requirements are being addressed. - ✔✔Inspection Test Plan
✔✔When are the NACE/SSPC International surface preparation standards considered
binding?
A. Anytime surface preparation is performed
B. As a replacement for any ISO standard
C. When specified in the contract documents
D. When there is a conflict between the PDS and the specifications - ✔✔C. When
specified in the contract documents
✔✔You know that you are sensitive to amines but not polyamides. What document
would you review prior to arriving at the jobsite?
A. Inspection Plan
B. Coating application guide
C. The contractor's contract
D. Safety Data Sheet - ✔✔D. Safety Data Sheet
✔✔You are reviewing the documentation for a tank coating project, and you notice there
is a conflict between the specification and the PDS and the required DFT of the primer.
The owner is not reachable for clarification. What should you do?