AND SOLUTIONS GUARANTEE A+
✔✔The Government's policy is to try to resolve all contractual issues in controversy by
what? - ✔✔Mutual agreement at the contracting officer's level
✔✔What are examples for justification of emergency acquisitions flexibilities? - ✔✔The
President has issued a major disaster declaration, The acquisition is to facilitate the
defense against a nuclear attack against the United States, The acquisition is in support
of a contingency operation
✔✔What is a function that must be delegated to a CAO if the agency has not
designated the CO to perform it? - ✔✔Negotiation of forward pricing rate agreements
✔✔Which of the following is not an example of information technology? Software
development, A computer hard drive, building's digital thermostat, or modem - ✔✔digital
thermostat
✔✔When shall certified cost or pricing data be obtained? - ✔✔negotiated procurement
is expected to exceed $750,000
✔✔What technique promote the early exchange of information with industry? -
✔✔Market research
✔✔When evaluating a proposal, what rating method is an agency required to use to
assess the evaluation factors specified in the solicitation? - ✔✔agency may use any
method or combination of methods
✔✔Standard Form 44 is also known as what? - ✔✔Purchase Order—Invoice—Voucher
✔✔Under FAR Part 5, contract actions must be synopsized in the GPE if they exceed
what amount? - ✔✔$25,000
✔✔In which FAR Part is the Uniform Contract Format outlined? - ✔✔Part 15
✔✔What is required when a change order is not forward priced? - ✔✔Documentation of
the change order and an agreement to an equitable adjustment in contract terms
✔✔A contractor infringes on a copyright with the authorization of the Government. What
remedy is available to the copyright holder? - ✔✔A suit for monetary damages against
the Government in the Court of Federal Claims
, ✔✔In the FAR citation "FAR 25.1102(a)(2)," what is referred to by the number 11? -
✔✔Subpart 25.11
✔✔Which of the following contract types is generally used to acquire construction? -
✔✔Firm-fixed-price
✔✔Which of the following would be necessary for sealed bidding to be appropriate? -
✔✔The award will be made on the basis of price and price-related factors
✔✔Which of the following is true about acquisitions for which the World Trade
Organization Government Procurement Agreement applies? - ✔✔The contracting
officer must not include technical requirements in solicitations solely to preclude the
acquisition of eligible products
✔✔Who is generally responsible for granting approval of a contractor's purchasing
system? - ✔✔administrative contracting officer
✔✔The process of establishing a reasonable amount to be paid for supplies or services
is called what? - ✔✔Pricing
✔✔What is the term for the amount of money specified in a bond as the maximum
payment for which the surety is obligated? - ✔✔Penal amount
✔✔Which of the following is a true statement about the role of the Acquisition Team? -
✔✔The procurement policies and procedures that are used by members of the
Acquisition Team are outlined in the FAR
✔✔When is consent to subcontract generally required? - ✔✔When the contractor has
an approved purchasing system
✔✔When will the acquisition procedures of FAR Part 12? - ✔✔Performance-based
acquisition, Acquisition of a commercial-off-the-shelf item, Acquisition based on the
results of market research
✔✔What methods of contract financing is least preferred by the Government? -
✔✔Advance payment
✔✔Which of the following is the Government permitted to do after receipt of proposals?
- ✔✔Make an award without holding discussions, if the solicitation says this is intended
✔✔Which of the following public relations or advertising costs would be unallowable?
Hosting a ceremony to announce a new product, Participating in community service