VA HIC CERTIFIED QUALITY QUESTIONS AND ANSWERS
GRADED A+ ASSURED SUCCESS LATEST 2026/27
What is the first step after finishing concrete?
Screeding
Ice dam protection needs to be _____ from the edge of the
eaves?
24 inches
Prior to the installation of wood floor how long for
acclimation?
4-5 days
What kind of siding can be vertically installed?
Board and batten
What type of lime is used in below grade masonry?
Type M
What type of lime is used in structural grade masonry?
,2
Type S
When building a masonry wall where do you start?
From the corner to the center
A door frame consists of what parts?
1 header 2 side jambs
What is the mayor advantage of icynene foam over
polyurethane foam?
Better and greater rate of expansion
What is the MAXIMUM threshold height for R-3 egress door?
1/2 inches
Door casing should be?
Nailed to trimmer stud and then chalked to the wall
What is best to use when installing hardwood floor?
Cut nails
, 3
When installing ceiling drywall, end butt joints should?
Be staggered
How should furring strips be installed?
Vertically nailed to the wood studs at 16 apart
When installing a run of wall cabinets the cabinets should?
With hanger rail
MINIMUM distance between screws on 1/2 inch drywall?
12 inches
When installing shoe molding on a base board over hardwood
floor the shoe molding should be?
Nailed to the base board only
What controls the flow of paint in an airless sprayer?
Orifice