Q1. Which document provides the primary basis for
understanding the fire-resistance rating requirements for
structural members?
A) ASTM E119
B) NFPA 101
C) IBC (International Building Code)
D) UL 263
Correct Answer: C
Rationale: The IBC specifies the fire-resistance ratings for
structural members and is the primary code document setting
requirements for fire-resistive construction in buildings .
,Page 2 of 130
Q2. Which document governs the overall requirements for
special inspections, including fire-resistive material inspections, in
the ICC exam?
A) NFPA 101 (Life Safety Code)
B) IBC Chapter 17
C) OSHA 1926 Subpart F
D) ASCE 7
Correct Answer: B
Rationale: IBC Chapter 17 outlines the special inspection
program, including fire-resistive material inspections, testing
requirements, and the Statement of Special Inspections .
Q3. According to IBC, who is prohibited from hiring the special
inspector to maintain impartiality?
,Page 3 of 130
A) The Building Official
B) The Contractor performing the work being inspected
C) The Owner
D) The Registered Design Professional (RDP)
Correct Answer: B
Rationale: To maintain impartiality and avoid conflicts of
interest, the contractor responsible for the work being inspected
cannot hire the special inspector. The owner or the RDP acting as
the owner’s agent typically employs the special inspector .
Q4. Who ultimately bears the responsibility for ensuring the
special inspector possesses an approved, current set of
construction plans and specifications on-site?
A) The Building Official
B) The Contractor
, Page 4 of 130
C) The Owner
D) The Registered Design Professional (RDP)
Correct Answer: B
Rationale: The contractor is responsible for maintaining
approved documents on site and ensuring all personnel, including
the special inspector, have access to current plans and
specifications .
Q5. What is a key role of the Spray-Applied Fireproofing
(SFRM) Special Inspector?
A) Designing fireproofing materials
B) Approving all construction schedules
C) Verifying correct application according to specifications
D) Managing project budgets
Correct Answer: C