Terms in this set (148) Hide definitions
What is NYC Chapter 33? Ch 33 = Safeguards During Construction or
What is Section 3301 and 3302? Demoltion
3301 = General
3302 = Definitions
What do you do when code does [3301.4.1]
not specifically state inspection is Any equipment (except hand tools) that affects
needed on an equipment? safety of public or property shall be inspected by a
COMPETENT PERSON designated by the
contractor using the equipment
This inspection shall be documented in an
inspection checklist signed and dated by the CP
Who is responsible for maintaining [3301.9]
construction/demo signs? The permit holder for the construction/demo work
If no active permits, then the building owner
page 1
,Name the (8) items that need to be [3301.9.1]
listed on a Project Information Panel 1. Rendering, elevation drawing, or zoning diagram
2. "Work in Progress" Title and specifying zoning
use
3. Anticipated project completion date
4. Property owner's corporate name, address,
phone #
5. Website address or phone # to contact
6. GC name and phone #
7. "To anonymously report unsafe conditions..call
311" in English and Spanish
8. Primary project permit (laminated)
Where should the Project [3301.9.1.2]
Information Panel be posted? On the fence on each perimeter
How high up? -if the perimeter is greater than 150ft, post at each
corner
- posted 4ft high from the ground to the bottom
edge of the panel
Name the specs of the Project [3301.9.1.4]
Information Panel and the (2) 6 ft wide x 4 ft high
exceptions Exceptions:
1) for demo project = 2'-4" wide x 4ft high
2) Sites that have street frontage less than 60 ft =
55" wide x 36.5" high
What contents should be on the SWS [3301.9.2.1]
parapet info panel? (3) 1) Street address of the site
2) Name of contractor responsible for site...if not,
then the owner
3) The statement "For more info, visit
NYC.GOV/BUILDINGS"
page 2
, Name the (4) requirements of [3301.9.2.2]
posting SWS parapet info panel 1) Posted along the long axis of the SWS
2) Shall not be posted above/below parapet
3) Between 3-6 feet from the left edge SWS or
property line
4) Centered above project info panel on Fence
What dimension shall the SWS [3301.9.2.4]
parapet info panel be? 3 ft high x 6 ft wide
When do you need site safety [3301.11]
orientation and refresher? - Orientation needed for each worker at any site
that requires SSM/SSC/superintendent
- Refresher is needed after (1) year for each worker
still working at the same site
Who can conduct the site safety [3301.11.3]
orientation and refresher? A qualified person designated by the permit holder
This qualified person shall have ability to
communicate with each worker
What contents should be included in [3301.11.4]
site safety orientation and refresher? 1) A review of safety procedures and any hazardous
activities to be performed at the site
2) Information pertaining to site safety training SST
as required in Section 3321
Describe how the site safety [3301.11.5]
orientation and refresher is recorded Records shall be maintained by permit holder and
kept at the jobsite
1) Date and time of orientation/refresher
2) Name, title, and company of each worker
3) Name, title, company, and signature of the
qualified person who conducted the orientation