EXAMINATION ACTUAL EXAM COMPLETE
QUESTIONS AND DETAILED SOLUTIONS
LATEST UPDATE THIS YEAR JUST RELEASED
California Roofing Contractor Examination (C-39) –
The California Roofing Contractor Examination is
required for applicants seeking the C-39 Roofing
Contractor license through the California Contractors
State License Board. The exam evaluates a candidate's
ability to safely plan, estimate, supervise, install, repair,
maintain, and manage roofing projects in compliance with
California laws, building codes, safety regulations,
contract requirements, and accepted roofing industry
practices.
Exam Coverage
Roof deck preparation and evaluation
Roofing safety requirements and fall protection
Personal protective equipment and jobsite safety
Roofing tools, equipment, and maintenance
Roofing materials identification and selection
, Built-up roofing systems
Modified bitumen roofing systems
Single-ply membrane roofing systems
Spray polyurethane foam roofing
Metal roofing systems
Tile roofing systems
Shingle roofing systems
Slate roofing systems
Roof drainage systems
Flashing installation and repair
Waterproofing principles
Moisture control and ventilation
Roof insulation systems
Roof coatings and restoration
Roofing estimates and bidding
Material quantity calculations
Reading plans and specifications
Building code compliance
Roofing repairs and maintenance
Leak detection and troubleshooting
, Project planning and scheduling
Quality control procedures
Environmental regulations
Hazard communication requirements
Equipment operation and inspection
Customer relations and documentation
Contract administration
Subcontractor coordination
Inspection procedures
Wind uplift considerations
Fire-resistance requirements
Energy efficiency requirements
Roof penetrations and accessories
Weather impacts on roofing installation
Construction mathematics
Roofing project supervision
Question 1
A roofing contractor notices deteriorated roof decking
beneath an existing shingle roof during a replacement
, project. What should be done before installing new roofing
materials?
A. Install shingles directly over damaged decking
B. Cover defects with underlayment only
C. Replace or repair damaged decking before proceeding
D. Add extra fasteners through defective decking
Answer: C
Rationale: Sound decking provides structural support and
proper fastening. Roofing materials should not be installed
over deteriorated substrates.
Question 2
During a steep-slope roofing project, workers are exposed
to potential falls exceeding regulatory thresholds. Which
control should be implemented first?
A. Ignore the hazard if workers are experienced
B. Implement approved fall-protection systems
C. Increase production speed
D. Use longer ladders only
Answer: B
Rationale: Fall protection is a primary safety requirement
and significantly reduces injury risk during roofing
operations.