⩥ According to the IBC, the "blank" is the responsible for the approval
of a person's qualifications to act as a special inspector.
Answer: code official. 2009 IBC, Section 1704.1
⩥ According to the IBC, discrepancy corrections are made known to the
building official by:
Answer: final report. 2009 IBC, Section1704.1.2
⩥ When is the code official to be made aware of a discrepancy found
during a special inspection?
Answer: If it is not corrected by the contractor. 2009 IBC, Section
1704.1.2
⩥ According to the Model Program for Special Inspection, the special
inspector is to document work that is nonconforming:
Answer: In a written report - Section II B 4 - Model Programs
⩥ According to the Model Program for Special Inspection, the special
inspector is to prepare written report of inspection:
,Answer: After each inspection visit - Section II B 5 - Model Programs
⩥ According to the Model Program for Special Inspection, which of the
following items does not need to be included in each inspection report?
Answer: Description of discussions with the contractor - Section B 5 -
Model Programs
⩥ According to the Specification for Structural Joints using high
strength bolts, the nominal diameter of standard bolt holes shall be how
much larger than the nominal bolt diameter?
Answer: 1/16 inch - Specification for Structural Joints Table 3.1
⩥ Discrepancies in the work shall be brought to the immediate attention
of the "blank" for corrective action.
Answer: the contractor - 2009 IBC, Section 1704.1.2.
⩥ The special inspector shall furnish inspection reports to the "blank"
and to the "blank"?
Answer: Building Official and Registered Design professional
⩥ The special inspector shall provide continuos inspection of:
Answer: Single-pass fillet welds greater than 5/16 inch in size - 2099
IBC, Table 1704.3, Item 5.3
, ⩥ The special inspections required by this code are not required where
the work is done on the premise of a?
Answer: Approved fabricator - 2009 IBC, Section 1704.2.2
⩥ The special inspection of the steel fabrication process shall not be
required where the fabricator does not perform any?
Answer: heating operations - 2009 IBC, Section 1704.3, Exceptions # 1
⩥ According to the Specifications for Structural Steel Buildings, ASTM
Standard "blank" is to be used for the material test for steel sheets.
Answer: A568 - Section A31, Specifications for Structural Steel
Buildings
⩥ According to the Specifications for Structural Steel Buildings, the
"blank" conducts the material tests for identification of the structural
steel.
Answer: Fabricator or Testing Laboratory - Section A31, Specifications
for Structural Steel Buildings.
⩥ According to the Specifications for Structural Steel Buildings, which
of the following steel members are allowed to be unidentified steel?
Answer: Unimportant members, where their physical properties and
weldability would not affect the structure strength - Section A31b,
Specifications for Structural Steel Buildings