What are some items you would need to communicate? -
ANSWER-Start and quit times. Break times and locations.
Special owner or GC rules. Productivity expectations. Safety.
Cell phone policy. Discrimination and harassment policies.
What to do if they are hurt. What to do if they can't come to
work. Where to store tools.
Describe how to handle a termination for cause? - ANSWER-A
shirt you have complied with company policy in the CBA with
regards to warnings. Make sure you have a documented any
verbal or written warnings. I sure you have all the facts. Speak
to the crew member in private, away from the rest of your crew.
Document the termination.
What is the purpose of a separation notice? - ANSWER-
To identify the
, circumstances surrounding a
termination.
What is the most important piece of job site documentation?
- ANSWER-The
Daily
Log.
What information is needed on the daily log? - ANSWER-What
work has been
done. Problems. Safety issues. Deliveries. Subcontractors
on site. Weather
conditions. Rental equipment on site. Company-owned
equipment on site. Any
verbal instructions received. Meetings
attended.
What are submittals? - ANSWER-Specs of materials and
equipment to be used
on the project which are sent to the architect and
engineer for approval.
Should you install material or equipment before it has been
approved, even
though it is in the spec? - ANSWER-No, only with the
project manager.