Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

NASCLA SAMPLE EXAM ACTUAL QUESTIONS AND VERIFIED AND 100% VERIFIED ANSWERS ALREADY GRADED A+

Beoordeling
-
Verkocht
-
Pagina's
24
Cijfer
A+
Geüpload op
20-05-2026
Geschreven in
2025/2026

This comprehensive NASCLA sample exam guide features actual exam questions with 100% verified correct answers—designed for aspiring general contractors preparing for the NASCLA Commercial General Contractor Exam. Covering all core domains including construction safety (OSHA compressed air cleaning—30 psi maximum with PPE; oxygen cylinder storage—20 feet from fuel gas; trench egress—25 feet maximum; fall protection—guardrails required when deck is 30 inches above grade, walkways 18 inches wide require fall arrest; radiant heater clearance—36 inches; incident reporting to OSHA within 8 hours of worker death; competent person vs engineer for shoring changes; personal protective equipment employer responsibility), contract law and project management (lien waivers—unconditional lien release in exchange for final payment prevents paying twice; indemnification clauses—have contract reviewed by attorney; contract ambiguity interpreted against party who wrote it; retainage—percentage withheld from progress payment; schedule of values progress payment calculation; change order pricing including overhead and profit; substantial completion—as-built drawings provided to owner; subcontractor selection based on ability to add value), building codes and construction methods (IBC plywood subfloor minimum 1/2 inch for 16-inch joist spacing; duplex nails for concrete forms; truss out-of-plumb maximum 1.5 inches for 20-foot span; gypsum ceiling framing spacing 24 inches maximum for 1/2 inch; #5 rebar diameter 5/8 inch; anchor bolts for open web joists 2-1/2 inch; nonload bearing metal stud most cost efficient 25 ga; masonry mortar concave joint best freeze protection; post-tensioning—tendons encased in HDPE sheathing prior to pour; waffle slabs use pan forms; cellular concrete fireproofing for steel beams; sheet piles for horizontal loads; brick veneer carries own weight; cavity minimum 2 inches), accessibility and ADA (egress doors open in direction of travel when occupant load 50; elevator call buttons arranged in telephone pattern, raised or flush; accessible manual swinging door pull-side clearance 18 inches; front-loading washing machine offset 24 inches; non-sliding egress door threshold maximum 1/2 inch for R-3 occupancy; parking lot handicapped spaces—2 spaces for 30 spaces), environmental and lead safety (pre-1978 renovation disturbing 2 sq ft paint—distribute EPA lead pamphlet; stormwater pollution plan required when project disturbs one or more acres; grey water excludes kitchen sink; unconditioned space ventilation to control moisture), soil and excavation (proctor test for soil compaction value; swell factor 25% increases hauling and decreases efficiency; suggested angle of repose for compacted sharp sand 1-1/2:1; trench box excavation depth below box 2 feet; slot dozing for short distance downgrade material movement; manual soil tests exclude slump test), concrete and curing (freezing temperatures lengthen curing time; controlled drying for proper curing; vibratory action allows stiffer mixture with larger coarse aggregate; compacted granular base for concrete curb minimum 6 inches; polyethene moisture barrier under slab joint overlap 6 inches), financial management (balance sheet formula—assets = liabilities + owners equity; debt carried three years listed as current liability; general overhead includes administrative expenses; separate journal for disbursements and payroll for large company), and green building (green construction reduces energy consumption 30-36%). Ideal for NASCLA exam candidates, general contractor license preparation, commercial building contractor exams, and construction management professionals.

Meer zien Lees minder
Instelling
NASCLA Sample
Vak
NASCLA Sample

Voorbeeld van de inhoud

NASCLA SAMPLE EXAM ACTUAL QUESTIONS AND
VERIFIED AND 100% VERIFIED ANSWERS ALREADY
GRADED A+



When may compressed air be used to clean dust from equipment
Only when the pressure is reduced to 50 psi maximum and personal
protective equipment is on place
Only when the pressure is reduced to 30 psi or less and personal
protective equipment is provided
Never
Only when the pressure is reduced to less than 45 psi - ANS... -Only
when the pressure is reduced to 30 psi or less and personal protective
equipment is provided

Which of the following documents are primarily used by the contractor
and architect to monitor quality?
Construction drawings
Contract addenda
Meeting Minutes
Submittals, shop drawings, and samples - ANS... -Submittals, shop
drawings, and samples

In order to protect the owner and contractor from lien filings, what
document is provided by a subcontractor in exchange for final payment?
Partial lien release
Unconditional lien release
Conditional lien release
Notice of completion - ANS... -unconditional lien release

What does a lien waiver release the owner from?
Paying the contractor for extra services
Paying twice for services or materials
The right to claim a lien

,Needing to file a notice of commencement - ANS... -paying twice for
services or materials

A renovation project is to begin on a pre-1978 housing project. It will
require that more than 2 square feet of painting surface be removed and
disturbed. What should the contractor do prior to beginning?
-Distribute an EPA pamphlet entitled "Protect your family from lead in
your home" to the property owner or adult occupant
-Submit a lead abatement notice to the EPA within 5 days of starting the
project
-Notify the owner and tenants of the project start
Inform the local health department of the project schedule - ANS... -
Distribute an EPA pamphlet entitled " Protect your family from lead in
your home" to the property owner or adult occupant

Which of the following is not a concern for a precast concrete contractor
during a reconstruction meeting?
Field layout and verification
Developing an erection plan
Maintaining anticipated overhead and profit margins
Determining site conditions - ANS... -Maintaining anticipated overhead
and profit margins

The international building code states that the minimum thickness of
plywood species group | that may be used for subfloor joists spaced 16
inches on center is :
1/2
3/8
3/4
7/8 - ANS... -1/2

When a contract requires the contractor to indemnify the owner for any
liability the owner may incur under he should:
Have the contract reviewed by an attorney
Ask for a liquidated damages clause

, Ask for a cost plus type contract
Obtain higher performance bond - ANS... -Have the contract reviewed
by an attorney


Which of the following is included in a company's general overhead
costs?
Performance Bonds
Withholding Taxes
Costs for equipment purchase and rentals
The company's administrative expenses - ANS... -The company's
administrative expenses

What is the purpose of ventilating unconditioned spaces?
To control moisture
Dehumidification
Control oxygen levels
Temperature Control - ANS... -To control moisture

Oxygen Cylinders shall be stored:
Separate from fuel gas cylinders a minimum of 10 ft
Separate from fuel gas cylinders a minimum of 20 ft
In a centrally located air tight closet
In a storage locker - ANS... -Separate from fuel gas cylinders a
minimum of 20 ft

What size diameter anchor bolts should open web joists have at each
end?
1 1/2"
2 1/2"
3 1/2"
4 1/2" - ANS... -2 1/2"

When should duplex nails be used?
When building concrete forms

Geschreven voor

Instelling
NASCLA Sample
Vak
NASCLA Sample

Documentinformatie

Geüpload op
20 mei 2026
Aantal pagina's
24
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$15.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
PrepPulse

Maak kennis met de verkoper

Seller avatar
PrepPulse NURSING, ECONOMICS, MATHEMATICS, BIOLOGY, AND HISTORY MATERIALS BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS, AND STUDY GUIDE MATERIALS WITH GUARANTEED A+ I am a dedicated medical practitioner with diverse knowledge in matters
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
-
Lid sinds
2 weken
Aantal volgers
0
Documenten
177
Laatst verkocht
-
ExamSmart

Exams feel overwhelming, but the right notes change everything. Here you'll find easy-to-follow summaries, step-by-step solutions, and practice materials that turn tough topics into manageable pieces. I create everything to match your actual exam board and keep it updated so you're never studying the wrong thing. Let's make your next exam your best one.

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen