1. What is the primary purpose of project integration
management?
A. Managing project procurement
B. Coordinating all project processes and activities
C. Estimating project costs
D. Assigning project resources
Rationale: Integration management ensures all project
components work together effectively throughout the project
lifecycle.
Correct Answer: B. Coordinating all project processes and
activities
2. Which document formally authorizes a project?
A. Scope statement
B. Business case
C. Project charter
D. Risk register
,Rationale: The project charter officially authorizes the project
and gives the project manager authority to use organizational
resources.
Correct Answer: C. Project charter
3. What is the main objective of stakeholder management?
A. Reducing project cost
B. Increasing project duration
C. Identifying and engaging project stakeholders effectively
D. Eliminating project risks
Rationale: Stakeholder management ensures stakeholders are
identified, understood, and appropriately engaged.
Correct Answer: C. Identifying and engaging project
stakeholders effectively
4. Which project management approach is most flexible and
iterative?
A. Waterfall
B. Predictive
C. Agile
D. Linear
Rationale: Agile allows adaptive planning and iterative
development throughout the project lifecycle.
,Correct Answer: C. Agile
5. What does a Work Breakdown Structure (WBS) represent?
A. Financial report
B. Organizational hierarchy
C. Decomposition of project deliverables into smaller
components
D. Risk assessment document
Rationale: WBS breaks project work into manageable sections
for planning and control.
Correct Answer: C. Decomposition of project deliverables into
smaller components
6. Which knowledge area focuses on ensuring the project
includes all required work?
A. Scope management
B. Resource management
C. Procurement management
D. Communication management
Rationale: Scope management defines and controls what work
is included in the project.
Correct Answer: A. Scope management
, 7. What is scope creep?
A. Delayed project completion
B. Uncontrolled expansion of project scope without
adjustments
C. Budget reduction
D. Resource shortage
Rationale: Scope creep occurs when additional features or work
are added without proper approval or control.
Correct Answer: B. Uncontrolled expansion of project scope
without adjustments
8. Which scheduling tool displays project tasks against time?
A. Pareto chart
B. Fishbone diagram
C. Gantt chart
D. SWOT analysis
Rationale: Gantt charts visually represent project activities
along a timeline.
Correct Answer: C. Gantt chart
9. Critical Path Method (CPM) identifies:
A. Project budget
B. Longest sequence of dependent tasks