Propane - Preparing to Run Propane Test -
correct answer ✅Step 1: Verify Propane in container - briefly open
outage valve and listen for release of vapor
Propane - Setting the Pressure -
correct answer ✅Step 1: Connect a calibrated manometer-
connect manometer to barbed fitting
Propane - Lockup Pressure Test -
correct answer ✅Step 1: Prepare for and perform lock up test -
close the orifice valve on test apparatus while watching manometer
measurement.
Propane - Timed Pressure Drop Test -
correct answer ✅Step 1: Prepare for times pressure drop test -
close the service valve fully
Propane - Bubble Solution Test -
correct answer ✅Step 1: Perform bubble test - open service valve
and bubble test all fittings that had been removed and reinstalled
during test procedures using detection solution
, RVTI - PDI Exam Questions & Answers
(Grade A+)
Water - Fresh Water System -
correct answer ✅Step 1: Pump strainer - inspect water pump
strainer, clean if 'tank trash' is visible
Water - Leak Test -
correct answer ✅Step 1: Leak Test - turn off the city water
Water - Fixture Flow Test -
correct answer ✅Step 1: Level RV - Orient RV into level position
Electric - Battery Inspection -
correct answer ✅Step 1: Battery Box - Confirm battery is vapor
tight from the inside of the RV and properly vented
Electric - Converter Output Circuits -
correct answer ✅Step 1: Fuses and Circuit Breaker - visually
inspect fuses or circuit breakers
Electric - Power Converters -
correct answer ✅Step 1: Documentation and Prepare - Assemble
documentation and plug coach into AC power source
(Grade A+)
Propane - Preparing to Run Propane Test -
correct answer ✅Step 1: Verify Propane in container - briefly open
outage valve and listen for release of vapor
Propane - Setting the Pressure -
correct answer ✅Step 1: Connect a calibrated manometer-
connect manometer to barbed fitting
Propane - Lockup Pressure Test -
correct answer ✅Step 1: Prepare for and perform lock up test -
close the orifice valve on test apparatus while watching manometer
measurement.
Propane - Timed Pressure Drop Test -
correct answer ✅Step 1: Prepare for times pressure drop test -
close the service valve fully
Propane - Bubble Solution Test -
correct answer ✅Step 1: Perform bubble test - open service valve
and bubble test all fittings that had been removed and reinstalled
during test procedures using detection solution
, RVTI - PDI Exam Questions & Answers
(Grade A+)
Water - Fresh Water System -
correct answer ✅Step 1: Pump strainer - inspect water pump
strainer, clean if 'tank trash' is visible
Water - Leak Test -
correct answer ✅Step 1: Leak Test - turn off the city water
Water - Fixture Flow Test -
correct answer ✅Step 1: Level RV - Orient RV into level position
Electric - Battery Inspection -
correct answer ✅Step 1: Battery Box - Confirm battery is vapor
tight from the inside of the RV and properly vented
Electric - Converter Output Circuits -
correct answer ✅Step 1: Fuses and Circuit Breaker - visually
inspect fuses or circuit breakers
Electric - Power Converters -
correct answer ✅Step 1: Documentation and Prepare - Assemble
documentation and plug coach into AC power source