Define Scope, Outputs - CORRECT ANSWER-Project scope statement
Project documents updates
Create WBS, Inputs - CORRECT ANSWER-Project Management Plan, Project documents, EEFs,
OPAs
Create WBS, Tools & Techniques - CORRECT ANSWER-Expert judgement, Decomposition
Create WBS, Outputs - CORRECT ANSWER-Scope baseline
Project documents updates
Validate Scope, Inputs - CORRECT ANSWER-Project Management Plan, Project documents,
Verified deliverables, Work performance data
Validate Scope, Tools and Techniques - CORRECT ANSWER-Inspection, Decision making
Validate Scope, Outputs - CORRECT ANSWER-Accepted deliverables, Work performance
information, Change requests, Project document updates
,Control Scope, Inputs - CORRECT ANSWER-Project Management Plan, Project documents, Work
performance data, OPAs
Control Scope, Tools & Techniques - CORRECT ANSWER-Data analysis
Control Scope, Outputs - CORRECT ANSWER-Work performance information, Change requests,
Project Management Plan updates, Project document updates
Plan Schedule Management, Inputs - CORRECT ANSWER-Project Charter, Project Management
Plan, EEFs, OPAs
Plan Schedule Management, Tools & Techniques (sc) - CORRECT ANSWER-Expert judgement,
Data analysis, Meetings (sc)
Plan Schedule Management, Outputs - CORRECT ANSWER-Schedule Management Plan
Define Activities, Inputs - CORRECT ANSWER-Project Management Plan, EEFs, OPAs
Define Activities, Tools & Techniques - CORRECT ANSWER-Expert judgement, Decomposition,
Rolling wave planning, Meetings
Define Activities, Outputs - CORRECT ANSWER-Activity list, Activity attributes, Milestone list,
Change requests, Project Management Plan updates
Sequence Activities, Inputs - CORRECT ANSWER-Project Management Plan, Project documents,
EEFs, OPAs
, Sequence Activities, Tools & Techniques - CORRECT ANSWER-Precedence diagramming method
(PDM)
Dependency determination
Leads and lags
Project Management Information System (PMIS)
Estimate Activity Durations, Inputs (e) - CORRECT ANSWER-Project Management Plan, Project
documents, EEFs, OPAs (e)
Estimate Activity Durations, Tools & Techniques - CORRECT ANSWER-Expert judgement,
Analogous estimating, Parametric estimating, Three-point estimating, Bottom-up estimating,
Data analysis, Decision making, Meetings
Estimate Activity Durations, Outputs - CORRECT ANSWER-Duration estimates, Basis of
estimates, Project document updates
Develop Schedule, Inputs (sc) - CORRECT ANSWER-Project Management Plan, Project
documents, Agreements, EEFs, OPAs (sc)
Develop Schedule, Tools & Techniques - CORRECT ANSWER-Schedule network analysis
Critical path method
Resource optimization techniques
Data Analysis
Leads and lags
Schedule compression
PMIS
Agile release planning