Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

NPDES LEVEL 1A PRACTICE TEST — 2025/2026 150+ Advanced Questions: BMPs, Soil Erosion, Sediment Control, Permit Rules & Georgia Compliance

Rating
-
Sold
-
Pages
51
Grade
A+
Uploaded on
24-05-2026
Written in
2025/2026

NPDES LEVEL 1A PRACTICE TEST — 2025/2026 150+ Advanced Questions: BMPs, Soil Erosion, Sediment Control, Permit Rules & Georgia Compliance

Institution
Course

Content preview

🌊 NPDES LEVEL 1A PRACTICE TEST —
2025/2026
150+ Advanced Questions: BMPs, Soil Erosion, Sediment
Control, Permit Rules & Georgia Compliance


SECTION 1: NPDES PERMIT FUNDAMENTALS &
REGULATORY FRAMEWORK (Questions 1–30)


1. Under the Clean Water Act Section 402, what does the NPDES permit program
regulate?

 A) Air emissions from construction sites
 B) Discharges of pollutants from point sources into waters of the United States ✅
(correct answer)
 C) Solid waste disposal at construction sites
 D) Wetland fill activities under Section 404

Rationale: Section 402 of the Clean Water Act (33 U.S.C. §1342) established the NPDES permit
program — regulating point source discharges of pollutants (including stormwater) into
navigable waters (Waters of the U.S.).



2. In Georgia, which agency administers the NPDES Construction General Permit (CGP)?

 A) U.S. Environmental Protection Agency Region 4
 B) Georgia Environmental Protection Division (EPD) ✅ (correct answer)
 C) Georgia Department of Transportation
 D) Georgia Soil and Water Conservation Commission

Rationale: Georgia is an EPA-authorized state — the Georgia Environmental Protection
Division (EPD) under the Georgia Department of Natural Resources administers the NPDES
program through the Georgia Stormwater Management Manual.

,3. What is the minimum land disturbance acreage threshold requiring an NPDES
Construction General Permit in Georgia?

 A) 0.5 acres
 B) 1 acre ✅ (correct answer)
 C) 2 acres
 D) 5 acres

Rationale: Per Georgia EPD's NPDES CGP, land disturbance activities disturbing 1 or more
acres (or less than 1 acre if part of a larger common plan of development disturbing 1+ acres)
require coverage under the permit.



4. What is a "common plan of development" under NPDES regulations?

 A) A municipal stormwater management plan
 B) A contiguous area where multiple separate and distinct construction activities may be
taking place at different times on different schedules under one plan ✅ (correct answer)
 C) A regional watershed protection plan
 D) A shared BMP maintenance agreement between adjacent property owners

Rationale: A "common plan of development or sale" means the total area of a larger project
must be considered — even if individual phases disturb less than 1 acre, if the overall plan
disturbs 1+ acres, each phase needs permit coverage.



5. What federal regulation specifically requires construction site operators to implement
BMPs for stormwater control?

 A) 40 CFR Part 122 ✅ (correct answer)
 B) 40 CFR Part 401
 C) 40 CFR Part 503
 D) 40 CFR Part 260

Rationale: 40 CFR Part 122 contains NPDES permit regulations including construction
stormwater requirements. The EPA's 2017 Construction General Permit (CGP) issued under
this authority provides the federal framework.



6. What is a "Notice of Intent" (NOI) in the context of Georgia's NPDES Construction
General Permit?

 A) A notification to adjacent property owners of upcoming construction

,  B) A formal application filed with Georgia EPD to obtain coverage under the
Construction General Permit before land disturbance begins ✅ (correct answer)
 C) A notice that a permit violation has occurred
 D) A document filed after construction completion

Rationale: The NOI is the mechanism for obtaining permit coverage — operators must submit a
complete NOI (with SWPPP certification) to Georgia EPD before beginning land-disturbing
activities.



7. Under Georgia's NPDES CGP, how many days before land disturbance must the NOI be
submitted?

 A) 3 days
 B) 5 days
 C) 7 days ✅ (correct answer)
 D) 14 days

Rationale: Georgia EPD requires the NOI to be submitted at least 7 calendar days prior to
commencement of land-disturbing activities. Coverage is automatic if no denial is issued within
this period.



8. What is a "Notice of Termination" (NOT) and when must it be filed in Georgia?

 A) A notice filed when a permit condition cannot be met
 B) A document filed with Georgia EPD to terminate permit coverage when a site
achieves final stabilization or ownership transfers ✅ (correct answer)
 C) A termination of a contractor's right to perform land-disturbing activities
 D) A notice that construction has temporarily ceased

Rationale: The NOT terminates NPDES permit responsibility — it should be filed when: (1) final
stabilization is achieved, (2) another operator has assumed control, or (3) a new permit has
been issued for the site.



9. What does "final stabilization" mean under Georgia's NPDES program?

 A) Installation of all permanent structures on the site
 B) All soil disturbance activities have ceased and a uniform perennial vegetative cover
with a density of 70% or more has been established, or equivalent permanent physical
erosion reduction methods have been employed ✅ (correct answer)
 C) All temporary BMPs have been removed from the site

,  D) The site has passed a final inspection by Georgia EPD

Rationale: Georgia EPD's CGP defines final stabilization as 70% vegetative cover density over
the entire site (excluding areas covered by permanent structures), or equivalent non-vegetative
stabilization.



10. What is the "Effluent Limitation Guideline" (ELG) for construction sites under federal
regulation?

 A) A numeric turbidity limit of 25 NTU at the point of discharge
 B) A requirement to use BMPs to minimize pollutant discharge — the technology-based
standard for construction stormwater ✅ (correct answer)
 C) A pH range of 6.0–9.0 for all discharges
 D) A sediment removal efficiency of 80%

Rationale: EPA's 2009 Effluent Limitation Guideline for construction sites requires use of
BMPs. The numeric turbidity limit (13 NTU) was vacated by courts — the current requirement is
technology-based BMP implementation.



11. Under Georgia's Erosion and Sedimentation Act (O.C.G.A. §12-7), who is responsible
for ensuring BMPs are implemented on a construction site?

 A) The general contractor only
 B) The owner of the land, the person conducting land-disturbing activities, and the prime
contractor — jointly and severally ✅ (correct answer)
 C) Only the person who signed the NOI
 D) The local governing authority

Rationale: Georgia's E&S Act establishes joint and several liability — the landowner, land
disturber, and prime contractor all share responsibility for E&S control compliance.



12. What is the Georgia Erosion and Sedimentation Act's primary purpose?

 A) To regulate stormwater quantity from new development
 B) To protect Georgia's land and water resources from the adverse effects of accelerated
soil erosion and sedimentation from land-disturbing activities ✅ (correct answer)
 C) To establish minimum setbacks from water bodies for construction
 D) To regulate wetland activities in Georgia

Written for

Course

Document information

Uploaded on
May 24, 2026
Number of pages
51
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$15.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller
Seller avatar
profEve

Get to know the seller

Seller avatar
profEve Teachme2-tutor
Follow You need to be logged in order to follow users or courses
Sold
8
Member since
6 months
Number of followers
0
Documents
1299
Last sold
1 month ago

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions