Question 1
A homeowner asks you to build a masonry retaining wall over
4 feet high on a residential property in Tucson. No engineered
drawings exist. Under Arizona ROC rules, you must:
A) Build it as requested if the homeowner signs a waiver
B) Hire a professional engineer to design it
,Page 2 of 157
C) Use a standard masonry textbook detail
D) Apply for a handyman exemption
Correct Answer: B
Rationale: Arizona Administrative Code R4-9-108 requires
engineered plans for retaining walls >4 ft in height. A waiver
does not override code.
Question 2
You sign a contract for $12,000 with a client in Scottsdale. The
client cancels in writing 2 business days after signing. Under
Arizona’s prompt notification law, you must:
A) Keep 20% as restocking fee
B) Refund all money within 30 days
C) Refund all money within 10 business days
D) Sue for breach of contract
Correct Answer: C
Rationale: A.R.S. § 32-1158.01 gives a 3-business-day right
,Page 3 of 157
to cancel for home solicitation contracts. Full refund required
within 10 business days.
Question 3
Which is a valid reason for the Arizona Registrar of
Contractors to deny a masonry contractor license application?
A) A single bounced check for $50 that was repaid
B) A felony conviction for theft within the past 10 years
C) Filing personal bankruptcy 15 years ago
D) Not having a business website
Correct Answer: B
Rationale: A.R.S. § 32-1154 allows denial for felony
convictions involving fraud or theft within 10 years. Minor
financial issues are not disqualifying.
Question 4
You hold a dual license (B-1 general and C-47 masonry). On a
masonry-only job, your contract must:
A) List only the C-47 license number
, Page 4 of 157
B) List both license numbers
C) Use a generic handyman number
D) Omit the license number
Correct Answer: A
Rationale: ROC rules require the license number for the
specific classification under which the work is performed.
Question 5
A client refuses to pay the final 5,000ona5,000ona20,000
masonry fireplace. You have a signed contract. Before suing,
you must:
A) File a lien immediately
B) Send a notice of claim to the ROC
C) Send a 10-day notice of intent to lien (pre-lien)
D) Accept the loss as bad debt
Correct Answer: C
Rationale: A.R.S. § 33-992.01 requires a preliminary 10-day
notice for residential property before filing a mechanic’s lien.